Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
Free Practice Questions
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 10 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
When a sprint is over, when does the next sprint begin?
Correct
It beings immediately after the previous sprint are over
Incorrect
It beings immediately after the previous sprint are over
-
Question 2 of 10
2. Question
What is the relation between agile and scrum?
Correct
Agile is a methodology for project management and scrum is just a part of it. Agile is a practice and scrum is a procedure to pursue the practice.
Incorrect
Agile is a methodology for project management and scrum is just a part of it. Agile is a practice and scrum is a procedure to pursue the practice.
-
Question 3 of 10
3. Question
What is the use of the Burn-up chart?
Correct
Burn-up charts show how much work is completed in a project. It is used to trace the progress of work in a project.
Incorrect
Burn-up charts show how much work is completed in a project. It is used to trace the progress of work in a project.
-
Question 4 of 10
4. Question
What is zero sprints?
Correct
Zero sprints can be considered as the preparation for the first sprint in agile. It is the time before the first sprint starts where activities regarding the preparation of the first sprint are done.
Incorrect
Zero sprints can be considered as the preparation for the first sprint in agile. It is the time before the first sprint starts where activities regarding the preparation of the first sprint are done.
-
Question 5 of 10
5. Question
What are the two types of spikes?
Correct
Spike is used for activities related to design, or technical issues. There are two types of spikes namely, Functional and technical spikes.
Incorrect
Spike is used for activities related to design, or technical issues. There are two types of spikes namely, Functional and technical spikes.
-
Question 6 of 10
6. Question
What is Sashimi in Scrum?
Correct
Sashimi is a technique that plays an important role in the scrum. It is used to check the completion of work created by the developers.
Incorrect
Sashimi is a technique that plays an important role in the scrum. It is used to check the completion of work created by the developers.
-
Question 7 of 10
7. Question
Why is the use of automated testing encouraged in scrum?
Correct
Automated testing is used because it makes the delivery faster for the project.
Incorrect
Automated testing is used because it makes the delivery faster for the project.
-
Question 8 of 10
8. Question
What is the benefit of TTD(TestDriven Development)?
Correct
It helps to prove that the code is actually working and refactoring allows improvement of the design of the code with the first test results at a low cost.
Incorrect
It helps to prove that the code is actually working and refactoring allows improvement of the design of the code with the first test results at a low cost.
-
Question 9 of 10
9. Question
What is the burndown chart for?
Correct
In the Agile project, the burndown chart is a way to check how the team is progressing and see what is happening within the team during every sprint.
Incorrect
In the Agile project, the burndown chart is a way to check how the team is progressing and see what is happening within the team during every sprint.
-
Question 10 of 10
10. Question
What should be done when a Product Owner is permanently unavailable?
Correct
When the Product owner is permanently unavailable a new product owner should be appointed because the development team has its own role in making a decision for the team.
Incorrect
When the Product owner is permanently unavailable a new product owner should be appointed because the development team has its own role in making a decision for the team.