Quiz-summary
0 of 30 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
Information
PRINCE2 – Foundation Exam Premium Access
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 30 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- Answered
- Review
-
Question 1 of 30
1. Question
According to the right definition of a stakeholder in the PRINCE2 which of the following is the most suitable?
Correct
It is to be noted that the correct and accurate definition of a stakeholder in PRINCE2 goes by a person who is affected by the project and can affect the project.
Incorrect
It is to be noted that the correct and accurate definition of a stakeholder in PRINCE2 goes by a person who is affected by the project and can affect the project.
-
Question 2 of 30
2. Question
What’s the name of the Project Manager’s progress report in the Controlling a Stage process?
Correct
It should be noted that The Highlight Report, created in the ‘Study highlights’ operation.
Incorrect
It should be noted that The Highlight Report, created in the ‘Study highlights’ operation.
-
Question 3 of 30
3. Question
Which of the following is does not contribute to be an input to the activity Prepare the Risk Management Strategy?
Correct
You won’t recall any of the ‘operation description’ diagrams in the manual unless you’re blessed with a photographic memory. These do, however, provide a valuable guide to help you keep things straight when revising. Each activity has a summary diagram of the activity and the corresponding one here makes the inputs clear. However, Project Mandate is not used as an activity Prepare the Risk Management Strategy.
Incorrect
You won’t recall any of the ‘operation description’ diagrams in the manual unless you’re blessed with a photographic memory. These do, however, provide a valuable guide to help you keep things straight when revising. Each activity has a summary diagram of the activity and the corresponding one here makes the inputs clear. However, Project Mandate is not used as an activity Prepare the Risk Management Strategy.
-
Question 4 of 30
4. Question
Documents of progress generated during each stage will be forwarded to the members of the Project Board. What is the Project Manager doing to see if anyone else will get a copy sent?
Correct
The Communications Management Plan provides information of the communications receivers in its ‘Reporting’ section, and these communications comprise the Highlight Report. The thought in the manual about communications management and the Product Initiation Documentation (PID) section of Project Controls remains unclear, but the PID was not listed as an choice in this issue. Be careful: In PRINCE2 there is no such thing as a communications strategy. Some questions that include plausible-sounding response choices, so you need to be very careful about what’s PRINCE2 and what’s not, particularly if your organization is using the non-PRINCE2 word.
Incorrect
The Communications Management Plan provides information of the communications receivers in its ‘Reporting’ section, and these communications comprise the Highlight Report. The thought in the manual about communications management and the Product Initiation Documentation (PID) section of Project Controls remains unclear, but the PID was not listed as an choice in this issue. Be careful: In PRINCE2 there is no such thing as a communications strategy. Some questions that include plausible-sounding response choices, so you need to be very careful about what’s PRINCE2 and what’s not, particularly if your organization is using the non-PRINCE2 word.
-
Question 5 of 30
5. Question
Which of the following is included in the full Business Case as a PRINCE2 section?
Correct
A different program, the Benefits Review Program. There is no such thing as a PRINCE2 Benefits Realization Timeline and cost-benefit analysis is a strategy, not a Business Case leading. ‘Investment appraisal’ is a heading in Business Case PRINCE2.
Incorrect
A different program, the Benefits Review Program. There is no such thing as a PRINCE2 Benefits Realization Timeline and cost-benefit analysis is a strategy, not a Business Case leading. ‘Investment appraisal’ is a heading in Business Case PRINCE2.
-
Question 6 of 30
6. Question
What of the following methods determines how regulation of transition can be exercised?
Correct
The Technique for Configuration Management is wrongly called, as the name leads you to believe it just includes Configuration management. The technique generally also includes the management of problems and the monitoring of changes. Of course, configuration management is closely related to change control, but they aren’t the same thing.
Incorrect
The Technique for Configuration Management is wrongly called, as the name leads you to believe it just includes Configuration management. The technique generally also includes the management of problems and the monitoring of changes. Of course, configuration management is closely related to change control, but they aren’t the same thing.
-
Question 7 of 30
7. Question
Which of the following is used for recording when the business benefits are calculated in PRINCE2?
Correct
If you look at the exact words carefully, some questions are easier to answer. Here the word ‘plan’ in the name ‘Benefits Analysis Program’ indicates the solution, even though you haven’t already learned it.
Incorrect
If you look at the exact words carefully, some questions are easier to answer. Here the word ‘plan’ in the name ‘Benefits Analysis Program’ indicates the solution, even though you haven’t already learned it.
-
Question 8 of 30
8. Question
How does the Project Manager periodically review the Benefits Review Program during a delivery phase?
Correct
It should be remembered that benefits that come on stream during and after the project, not just at the end of the project. The Benefits Review Package lists all reviews of the benefits. As its name suggests, it is a program to test benefits and is not used to document benefits.
Incorrect
It should be remembered that benefits that come on stream during and after the project, not just at the end of the project. The Benefits Review Package lists all reviews of the benefits. As its name suggests, it is a program to test benefits and is not used to document benefits.
-
Question 9 of 30
9. Question
Which of the following phrases for the Initiating a Project cycle is part of the intent statement?
Correct
It is found that “establishing a solid foundation of the project under construction” is part of the purpose statement as mentioned in the process of Initiating a Project.
Incorrect
It is found that “establishing a solid foundation of the project under construction” is part of the purpose statement as mentioned in the process of Initiating a Project.
-
Question 10 of 30
10. Question
Which of the following is true for Baseline Products?
Correct
It is to be noted that those baselined goods are the ones you want to keep track of versions, maybe to look back on an earlier release.
Incorrect
It is to be noted that those baselined goods are the ones you want to keep track of versions, maybe to look back on an earlier release.
-
Question 11 of 30
11. Question
Reports of progress, generated during each level, are sent to members of the Project Board. What does the Project Manager do to see if anyone else can get a copy sent?
Correct
The Communications Management Plan includes information of the communications receivers in its ‘Reporting’ section, and these communications include the Highlight Sheet. Be careful: In PRINCE2 there is no such thing as a communications strategy.
Incorrect
The Communications Management Plan includes information of the communications receivers in its ‘Reporting’ section, and these communications include the Highlight Sheet. Be careful: In PRINCE2 there is no such thing as a communications strategy.
-
Question 12 of 30
12. Question
What PRINCE2 management tool should the Team Manager periodically review during work on a Work Package?
Correct
The Team Manager should be aware of what quality activity is needed on the products in the Work Package and be checking to ensure that those activities are being carried out. The Daily Log and Risk Register are the Project Manager’s responsibility, while the brief was left behind long ago when the Product Initiation Documentation (PID) was created. The Team Manager may also check the Risk Register, but this is not as central as the checks on the Quality Register.
Incorrect
The Team Manager should be aware of what quality activity is needed on the products in the Work Package and be checking to ensure that those activities are being carried out. The Daily Log and Risk Register are the Project Manager’s responsibility, while the brief was left behind long ago when the Product Initiation Documentation (PID) was created. The Team Manager may also check the Risk Register, but this is not as central as the checks on the Quality Register.
-
Question 13 of 30
13. Question
What is the name of the Project Manager’s progress report for the Controlling a Stage process?
Correct
It should be noted that the Highlight Report is produced by the Project Manager in the activity ‘Report highlights’.
Incorrect
It should be noted that the Highlight Report is produced by the Project Manager in the activity ‘Report highlights’.
-
Question 14 of 30
14. Question
Which of these is NOT an operation within the Managing Product Delivery process?
Correct
Review the Work Package Status is a PRINCE2 operation but it relates to reviewing the Work Package as part of the Managing a Stage process by the Project Manager.
Incorrect
Review the Work Package Status is a PRINCE2 operation but it relates to reviewing the Work Package as part of the Managing a Stage process by the Project Manager.
-
Question 15 of 30
15. Question
How does the Project Manager periodically review the Benefits Review Program during a delivery phase?
Correct
Note that benefits will come on stream in the course of the project, not just at the end and after. The Benefits Review Package lists all reviews of the benefits. As its name suggests, it is a program to test benefits and is not used to document benefits.
Incorrect
Note that benefits will come on stream in the course of the project, not just at the end and after. The Benefits Review Package lists all reviews of the benefits. As its name suggests, it is a program to test benefits and is not used to document benefits.
-
Question 16 of 30
16. Question
When a project manager estimates that a job package’s job will surpass the Project Manager’s overall time limit (tolerance) what will the team manager do?
Correct
Projections that a Work Package may surpass the specified limits must be identified immediately as part of the exception management process. If not, why limitations? The entire aim of them is to serve as a trigger for coverage.
Incorrect
Projections that a Work Package may surpass the specified limits must be identified immediately as part of the exception management process. If not, why limitations? The entire aim of them is to serve as a trigger for coverage.
-
Question 17 of 30
17. Question
When Project Managers note that a stage deviates from their schedule, what will they do when control action falls under the project board assigned authority limits?
Correct
The whole idea of giving the delegated authority is that, under those boundaries, everybody will get on with the job. The Project Director will plan and get on. It will be expressed in the flow of the activities in the process, and it is the substance of the ‘Take corrective action’ operation. Until setting the action on the train, the Project Manager may take advice but that may not be appropriate. The other response options suggest mandatory participation of others in the handling of each problem and this is simply not valid.
Incorrect
The whole idea of giving the delegated authority is that, under those boundaries, everybody will get on with the job. The Project Director will plan and get on. It will be expressed in the flow of the activities in the process, and it is the substance of the ‘Take corrective action’ operation. Until setting the action on the train, the Project Manager may take advice but that may not be appropriate. The other response options suggest mandatory participation of others in the handling of each problem and this is simply not valid.
-
Question 18 of 30
18. Question
How does the Team Manager do if a Team Manager finds a simpler way to do it and wants this recorded as a lesson learned that will benefit future projects?
Correct
The Checkpoint Report must report lessons to a Group Leader. Team managers do not issue Lesson Reports, nor do they make notes in the Lessons Log, which is the log of the Project Director. Plan Monitoring is mainly concerned with audit work, not active plan work such as lessons gathering.
Incorrect
The Checkpoint Report must report lessons to a Group Leader. Team managers do not issue Lesson Reports, nor do they make notes in the Lessons Log, which is the log of the Project Director. Plan Monitoring is mainly concerned with audit work, not active plan work such as lessons gathering.
-
Question 19 of 30
19. Question
How Project Managers do when project managers get a progress update from a team manager?
Correct
It is to be noted that for information, copy it to project board members.
Incorrect
It is to be noted that for information, copy it to project board members.
-
Question 20 of 30
20. Question
What plan can be developed for the ‘Accept a Work Package’ activity?
Correct
In this phase (Accepting a Work Package), it is the Team Plan which can be developed. But it’s ‘can’ because it’s optional for team plans.
Incorrect
In this phase (Accepting a Work Package), it is the Team Plan which can be developed. But it’s ‘can’ because it’s optional for team plans.
-
Question 21 of 30
21. Question
What is an operation in the Managing a Stage Boundary process?
Correct
It is to be noted that “reporting stage end” is an activity in the process Managing a Stage Boundary. This is the last activity in the process, as a look at the process model reveals.
Incorrect
It is to be noted that “reporting stage end” is an activity in the process Managing a Stage Boundary. This is the last activity in the process, as a look at the process model reveals.
-
Question 22 of 30
22. Question
What report(s) will the project manager build using the Closing a Project process?
Correct
It should be noted that the Project Manager creates only an end project report while using the process “Closing a Project Process”.
Incorrect
It should be noted that the Project Manager creates only an end project report while using the process “Closing a Project Process”.
-
Question 23 of 30
23. Question
When will a Step Boundary Management System be performed?
Correct
At the end of a level, just before the start of the next one. The exception is the final stage where then the Closing a Project process is used. Excluding the final stage of a project is a significant point, but the manual forgets to mention it, making this aspect of the intent statement very misleading.
Incorrect
At the end of a level, just before the start of the next one. The exception is the final stage where then the Closing a Project process is used. Excluding the final stage of a project is a significant point, but the manual forgets to mention it, making this aspect of the intent statement very misleading.
-
Question 24 of 30
24. Question
If, partway through a delivery stage of the project, the Project Board instructs the Project Manager to shut down the project prematurely:
Correct
A project PRINCE2 often takes advantage of the closure process. The tasks may be completed faster in a premature close than in a standard scheduled closure, but they are still finished. There is also a specific method to schedule a premature closure, as well as the other choice to schedule the originally scheduled closure.
Incorrect
A project PRINCE2 often takes advantage of the closure process. The tasks may be completed faster in a premature close than in a standard scheduled closure, but they are still finished. There is also a specific method to schedule a premature closure, as well as the other choice to schedule the originally scheduled closure.
-
Question 25 of 30
25. Question
PRINCE2 needs an analysis of the business case as part of Handling a Stage Boundary’s function. What Theory PRINCE2 primarily supports this?
Correct
The Business Case must at least be checked at the end of each point. With ‘Emphasis on benefits,’ be careful. It sounds pretty good but it is not one of the seven concepts of PRINCE2.
Incorrect
The Business Case must at least be checked at the end of each point. With ‘Emphasis on benefits,’ be careful. It sounds pretty good but it is not one of the seven concepts of PRINCE2.
-
Question 26 of 30
26. Question
If the Closure of a Project phase is used to close the project prematurely then:
Correct
If you look at the Process Model for Closing a Project it reveals a dotted line from the activity ‘Prepare premature proximity’ to the activity ‘Turn over Goods’ to demonstrate that certain items can be shipped.
Incorrect
If you look at the Process Model for Closing a Project it reveals a dotted line from the activity ‘Prepare premature proximity’ to the activity ‘Turn over Goods’ to demonstrate that certain items can be shipped.
-
Question 27 of 30
27. Question
How is the Quality Register modified in the Stage Boundary Management process?
Correct
The Quality Register/Management lists all the quality operations in one point so that when it’s completed each can be signed off – it serves as a kind of checklist. The stage boundary is where the list for the next stage is inserted into the log.
Incorrect
The Quality Register/Management lists all the quality operations in one point so that when it’s completed each can be signed off – it serves as a kind of checklist. The stage boundary is where the list for the next stage is inserted into the log.
-
Question 28 of 30
28. Question
What task is mostly responsible in the Closing a Project phase for the work?
Correct
The Project Manager will contact other project management team members and there is some work by Project Support and Quality Monitoring, but the vast majority of the termination work is the Project Manager’s responsibility.
Incorrect
The Project Manager will contact other project management team members and there is some work by Project Support and Quality Monitoring, but the vast majority of the termination work is the Project Manager’s responsibility.
-
Question 29 of 30
29. Question
The function is responsible at the end of a stage for updating the Benefits Review Plan when required?
Correct
It is to be noted that the project manager is responsible for most feedback on stage boundaries of the goods.
Incorrect
It is to be noted that the project manager is responsible for most feedback on stage boundaries of the goods.
-
Question 30 of 30
30. Question
Significant lessons that would be of interest to the company when carrying out more projects can be gained in any project. Why is the Closing a Project cycle used to ensure that these project experiences are passed on to the organization?
Correct
The Lessons Report is included at the End Project Report and then it is the responsibility of the Project Board to distribute the lessons to the relevant people within the company.
Incorrect
The Lessons Report is included at the End Project Report and then it is the responsibility of the Project Board to distribute the lessons to the relevant people within the company.