Quiz-summary
0 of 40 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
Information
PRINCE2 – Foundation Exam Premium Access
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 40 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- Answered
- Review
-
Question 1 of 40
1. Question
Which of these roles can’t be shared and just one person must fill-in?
Correct
It is to be noted PRINCE2 allows only one Project Manager (and only one Executive).
Incorrect
It is to be noted PRINCE2 allows only one Project Manager (and only one Executive).
-
Question 2 of 40
2. Question
What functions of the Project Board devote personnel resources to the project?
Correct
The Senior Supplier authorizes specialist resources, and the Senior User authorizes any user resource (such as to help specify requirements and take part in testing).
Incorrect
The Senior Supplier authorizes specialist resources, and the Senior User authorizes any user resource (such as to help specify requirements and take part in testing).
-
Question 3 of 40
3. Question
Which of these roles is optional and need not be filled in a PRINCE2 project?
Correct
It is to be noted that the work can be covered by the Project Manager, usually in a small project.
Incorrect
It is to be noted that the work can be covered by the Project Manager, usually in a small project.
-
Question 4 of 40
4. Question
Which of these roles is not part of the PRINCE2 project management team?
Correct
It is to be noted that quality assurance is an organizational function, external to the project.
Incorrect
It is to be noted that quality assurance is an organizational function, external to the project.
-
Question 5 of 40
5. Question
In which the PRINCE2 process is the project management team designed?
Correct
Specifically in the activity ‘Design and appoint the project management team’ comes under starting up a project.
Incorrect
Specifically in the activity ‘Design and appoint the project management team’ comes under starting up a project.
-
Question 6 of 40
6. Question
Which of the following is true about the release?
Correct
It is to be noted that a release is a collection of items, each with a registered version number, that works together. So in IT, a release could be a computer system of, say, five programs: version 4.5 of program 1, version 4.2 of program 2, version 6.8 of program 3, version 1.7 of program 4, and version 2.9 of program 5. A future release may only have some of the member programs updated, with the remainder being the same as in the previous release.
Incorrect
It is to be noted that a release is a collection of items, each with a registered version number, that works together. So in IT, a release could be a computer system of, say, five programs: version 4.5 of program 1, version 4.2 of program 2, version 6.8 of program 3, version 1.7 of program 4, and version 2.9 of program 5. A future release may only have some of the member programs updated, with the remainder being the same as in the previous release.
-
Question 7 of 40
7. Question
Who should appoint an appropriate person to the role of Project Manager if this is not done by the management of the company or the program?
Correct
If this is not done by corporate or program management, the Executive should appoint a suitable person to the role of Project Manager.
Incorrect
If this is not done by corporate or program management, the Executive should appoint a suitable person to the role of Project Manager.
-
Question 8 of 40
8. Question
Who’s responsible for the preparation of the Communications Management Strategy?
Correct
It is to be noted others can contribute and support but the responsibility lies with the Project Manager.
Incorrect
It is to be noted others can contribute and support but the responsibility lies with the Project Manager.
-
Question 9 of 40
9. Question
What are the three types of Project Assurance?
Correct
The three types of project insurance are
I: Business
II: User
III: SupplierIncorrect
The three types of project insurance are
I: Business
II: User
III: Supplier -
Question 10 of 40
10. Question
Which of these is not an acceptable set of roles in a PRINCE2 project for one person to cover?
Correct
It is to be noted Plan Monitoring must be Project Manager-independent. It is fine for one person to be the Project Board on a very small project and to cover all three board roles.
Incorrect
It is to be noted Plan Monitoring must be Project Manager-independent. It is fine for one person to be the Project Board on a very small project and to cover all three board roles.
-
Question 11 of 40
11. Question
It’s important to think through and record how a project achieves its required level of quality. In PRINCE2 which product records this detail?
Correct
It is to be noted the term ‘strategy’ is a gift for any aspect of ‘how’ something is going to be done, and for PRINCE2 that is risk, quality, configuration management (actually, how all changes are going to be managed) and communication.
Incorrect
It is to be noted the term ‘strategy’ is a gift for any aspect of ‘how’ something is going to be done, and for PRINCE2 that is risk, quality, configuration management (actually, how all changes are going to be managed) and communication.
-
Question 12 of 40
12. Question
Which Project Board role is responsible for ensuring that the project delivers things that are fit for purpose?
Correct
It is to be noted a representative of a program may attend board meetings, but that is not a board position, so quality or other obligations are not specified in PRINCE2.
Incorrect
It is to be noted a representative of a program may attend board meetings, but that is not a board position, so quality or other obligations are not specified in PRINCE2.
-
Question 13 of 40
13. Question
In which PRINCE2 product are Customer Quality Expectations first recorded?
Correct
The Overview of the Project Product Description (PPD) is created an early-in Start-Up. The customer quality expectations will continue to be included in the Project Initiation Documentation (PID), but ‘first recorded’ is specified in the question. There’s no such thing in PRINCE2 as the Project Output Register, by the way. There are quality records and although they can go to a file, that file is not a PRINCE2.
Incorrect
The Overview of the Project Product Description (PPD) is created an early-in Start-Up. The customer quality expectations will continue to be included in the Project Initiation Documentation (PID), but ‘first recorded’ is specified in the question. There’s no such thing in PRINCE2 as the Project Output Register, by the way. There are quality records and although they can go to a file, that file is not a PRINCE2.
-
Question 14 of 40
14. Question
Which sentence completes the statement of intent for the topic of Quality? The Quality theme aims at identifying and enforcing the means by which the project will be developed, and:
Correct
Verify products that are fit for purpose completes the purpose statement for the Quality theme? The purpose of the Quality theme is to define and implement the means by which the project will create and:
Incorrect
Verify products that are fit for purpose completes the purpose statement for the Quality theme? The purpose of the Quality theme is to define and implement the means by which the project will create and:
-
Question 15 of 40
15. Question
Which of these is NOT a role on a PRINCE2 Quality Review?
Correct
The executive is not a role in a PRINCE2 Quality Review.
Incorrect
The executive is not a role in a PRINCE2 Quality Review.
-
Question 16 of 40
16. Question
What is the name given to quality control by PRINCE2 while a product is still being developed to ensure that quality is ‘built-in’?
Correct
It is noted that more rote learning of terminology, although this term is more readily understood – and so memorable – than some others in the topic of Quality.
Incorrect
It is noted that more rote learning of terminology, although this term is more readily understood – and so memorable – than some others in the topic of Quality.
-
Question 17 of 40
17. Question
When is the Quality Management Strategy prepared in a PRINCE2 project?
Correct
The preparation of the strategy is covered by the Initiating a Project process, which in turn is part of the Initiation Stage work carried out.
Incorrect
The preparation of the strategy is covered by the Initiating a Project process, which in turn is part of the Initiation Stage work carried out.
-
Question 18 of 40
18. Question
Which of these statements are correct?
Correct
Quality Assurance is outside of the project while Project Assurance is inside the project and accountable to the Project Board – or members of the board are doing it themselves. Project Assurance is independent of the Project Manager, but the quality assurance is independent of the project as a whole, including its Project Board.
Incorrect
Quality Assurance is outside of the project while Project Assurance is inside the project and accountable to the Project Board – or members of the board are doing it themselves. Project Assurance is independent of the Project Manager, but the quality assurance is independent of the project as a whole, including its Project Board.
-
Question 19 of 40
19. Question
When should those attending a Quality Review receive a copy of the product to be reviewed?
Correct
It is to be noted that comments may be submitted to be placed on the agenda for consideration prior to analysis. That means people need to get the product on time
Incorrect
It is to be noted that comments may be submitted to be placed on the agenda for consideration prior to analysis. That means people need to get the product on time
-
Question 20 of 40
20. Question
Which of these would be a suitable entry in a project’s Acceptance Criteria?
Correct
It is to be noted the new system must have 99 percent availability with 1 percent maximum downtime would be a suitable entry in a project’s Acceptance Criteria
Incorrect
It is to be noted the new system must have 99 percent availability with 1 percent maximum downtime would be a suitable entry in a project’s Acceptance Criteria
-
Question 21 of 40
21. Question
Who’s responsible for approving the Project Plan?
Correct
The plan may be checked by Project Assurance, but it’s approved by the board. Any plan at the project or stage level must have Project Board approval.
Incorrect
The plan may be checked by Project Assurance, but it’s approved by the board. Any plan at the project or stage level must have Project Board approval.
-
Question 22 of 40
22. Question
What approach does PRINCE2 take to planning?
Correct
This supports the principle of ‘focus on products’.
Incorrect
This supports the principle of ‘focus on products’.
-
Question 23 of 40
23. Question
Which plan(s) are included in the Project Initiation Documentation (PID) below?
Correct
It is to be noted that Just the Project Plan is included in the Project Initiation Documentation (PID).
Incorrect
It is to be noted that Just the Project Plan is included in the Project Initiation Documentation (PID).
-
Question 24 of 40
24. Question
What are the three levels of planning in PRINCE2?
Correct
It is to be noted plans for exceptions aren’t standard. An exemption plan is usually at the level of a point, but maybe at the level of a project or include more than one phase.
Incorrect
It is to be noted plans for exceptions aren’t standard. An exemption plan is usually at the level of a point, but maybe at the level of a project or include more than one phase.
-
Question 25 of 40
25. Question
Which of the following is necessary for Authorizing a Stage or Exception Plan?
Correct
The Project Manager submits an End Stage Report for the job that has just been completed along with a Next Stage Plan or an Exemption Plan for the remainder of the current stage.
Incorrect
The Project Manager submits an End Stage Report for the job that has just been completed along with a Next Stage Plan or an Exemption Plan for the remainder of the current stage.
-
Question 26 of 40
26. Question
Product descriptions are written:
Correct
It is to be noted product descriptions for all identified products are written, and as soon as possible after the product needs are identified.
Incorrect
It is to be noted product descriptions for all identified products are written, and as soon as possible after the product needs are identified.
-
Question 27 of 40
27. Question
Which of the following shows the expected sequence of product development in a PRINCE2 project?
Correct
It is to be noted the keyword is ‘flow’.
Incorrect
It is to be noted the keyword is ‘flow’.
-
Question 28 of 40
28. Question
When is a Stage Plan developed for a delivery phase in a PRINCE2 project?
Correct
It is to be noted stage planning is covered by the Managing a Stage Boundary process which is triggered at the end of each stage except for the final stage of the project. When there is no other stage to plan, the Closing a Project process is instead called.
Incorrect
It is to be noted stage planning is covered by the Managing a Stage Boundary process which is triggered at the end of each stage except for the final stage of the project. When there is no other stage to plan, the Closing a Project process is instead called.
-
Question 29 of 40
29. Question
Which of the following statements is correct?
Correct
It is to be noted PRINCE2 takes a product-based or product-led approach to planning, but that doesn’t mean that other plans aren’t needed, just that the products are done first. An external product is something coming over the boundary of the project from outside. An external product is needed on the project, or it wouldn’t be included in the diagrams.
Incorrect
It is to be noted PRINCE2 takes a product-based or product-led approach to planning, but that doesn’t mean that other plans aren’t needed, just that the products are done first. An external product is something coming over the boundary of the project from outside. An external product is needed on the project, or it wouldn’t be included in the diagrams.
-
Question 30 of 40
30. Question
Within the PRINCE2 management product categories, which of the following is a report?
Correct
It is to be noted that all the PRINCE2 reports have the word ‘report’ in their title, with the sole exception of the Product Status Account. If you haven’t learned as far as change control, don’t worry about the Product Status Account . . . yet. The Highlight Report is the regular progress report sent by the Project Manager to the Project Board members and then to any other people designated in the Communications Management Strategy.
Incorrect
It is to be noted that all the PRINCE2 reports have the word ‘report’ in their title, with the sole exception of the Product Status Account. If you haven’t learned as far as change control, don’t worry about the Product Status Account . . . yet. The Highlight Report is the regular progress report sent by the Project Manager to the Project Board members and then to any other people designated in the Communications Management Strategy.
-
Question 31 of 40
31. Question
Which of these is NOT a PRINCE2 risk response?
Correct
It is to be noted there’s a response that’s ‘rejecting’ and maybe, unfortunately, starting with an ‘R’ as well. This is where acronyms such as AS RAFT and SEER only serve as memory joggers since you still need to remember exactly what the acronym letters stand for. A nasty question but to make the point about being sure of the acronyms is included here.
Incorrect
It is to be noted there’s a response that’s ‘rejecting’ and maybe, unfortunately, starting with an ‘R’ as well. This is where acronyms such as AS RAFT and SEER only serve as memory joggers since you still need to remember exactly what the acronym letters stand for. A nasty question but to make the point about being sure of the acronyms is included here.
-
Question 32 of 40
32. Question
Which of the following statements is correct?
Correct
It is to be noted in PRINCE2 the risk management is not optional. The Regular Log documents risks found during Start-Up, including when there is a strong need for structured monitoring of them. During initiation, the risks are then transferred to the Risk Register, when the Risk Register is available. Everyone, including Team Managers, is interested in recognizing risk. When doing team plans, team managers can also spot risks.
Incorrect
It is to be noted in PRINCE2 the risk management is not optional. The Regular Log documents risks found during Start-Up, including when there is a strong need for structured monitoring of them. During initiation, the risks are then transferred to the Risk Register, when the Risk Register is available. Everyone, including Team Managers, is interested in recognizing risk. When doing team plans, team managers can also spot risks.
-
Question 33 of 40
33. Question
Which term is used in PRINCE2 to describe something that could initiate a risk with a negative impact on objectives?
Correct
It is to be noted threats for negative risks, opportunities for positive risks.
Incorrect
It is to be noted threats for negative risks, opportunities for positive risks.
-
Question 34 of 40
34. Question
If a team member notices a new risk when working on a Work Package, how does that team member normally report it?
Correct
It is to be noted this question shouldn’t have been a problem unless all the PRINCE2 management products swim in your head and you start losing focus on what they all are about. The team members are not interested in the preparation of Checkpoint Reports or Highlight Reports. There’s no such thing as a Risk Report in PRINCE2. If products are starting to swim around, try to stand back a bit in your revision and
Incorrect
It is to be noted this question shouldn’t have been a problem unless all the PRINCE2 management products swim in your head and you start losing focus on what they all are about. The team members are not interested in the preparation of Checkpoint Reports or Highlight Reports. There’s no such thing as a Risk Report in PRINCE2. If products are starting to swim around, try to stand back a bit in your revision and
-
Question 35 of 40
35. Question
Three items are required to be successful in managing the risk. Two are that there is a need to identify and monitor risks. The third need is that it has risks:
Correct
It is to be noted that first two things for risks are that they need to be identified and controlled; the third thing is that it needs to be assessed.
Incorrect
It is to be noted that first two things for risks are that they need to be identified and controlled; the third thing is that it needs to be assessed.
-
Question 36 of 40
36. Question
What are the missing words from the following PRINCE2 definition of risk?
A risk is [?] that, should it occur, will have an effect on the achievement of objectives.Correct
It is to be noted that you need to be familiar enough with things like definitions, so you can quickly and accurately pick the right words. The keyword for risk is ‘uncertainty,’ so if you weren’t sure this is a good indication here.
Incorrect
It is to be noted that you need to be familiar enough with things like definitions, so you can quickly and accurately pick the right words. The keyword for risk is ‘uncertainty,’ so if you weren’t sure this is a good indication here.
-
Question 37 of 40
37. Question
Which of the following is not part of the PRINCE2 risk management procedure?
Correct
It is to be noted that resource is not part of the PRINCE2 risk management procedure.
Incorrect
It is to be noted that resource is not part of the PRINCE2 risk management procedure.
-
Question 38 of 40
38. Question
Which of the following statements are correct?
Correct
It is to be noted that the Risk Register is created during the Initiation of a Project process, not during Start-Up, and when the Risk Management Plan is being formulated.
Incorrect
It is to be noted that the Risk Register is created during the Initiation of a Project process, not during Start-Up, and when the Risk Management Plan is being formulated.
-
Question 39 of 40
39. Question
Which of the following are two commonly used measures of risk?
Correct
It is to be noted that proximity is another measure but that is not mentioned in the question. Probability and impact are common risk management measures in general and not just PRINCE2, hence the P – I Matrix.
Incorrect
It is to be noted that proximity is another measure but that is not mentioned in the question. Probability and impact are common risk management measures in general and not just PRINCE2, hence the P – I Matrix.
-
Question 40 of 40
40. Question
In a PRINCE2 project, which job is ultimately responsible for all aspects of risk management and to ensure that there is a risk management strategy for that?
Correct
Incorrect
It is to be noted that ultimately the Executive is responsible, though others may be doing risk-related work and have input.