Information
PRINCE2 – Foundation Exam Premium Access
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 30 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- Answered
- Review
-
Question 1 of 30
1. Question
Which of the following options complete the formulation of the Business Case theme intent statement?
“The theme of the Business Case is to create frameworks for deciding whether the project is (and remains) attractive, viable and achievable as a means of supporting:”Correct
According to the theme statement described follow:
“The theme of the Business Case is to create frameworks for deciding whether the project is (and remains) attractive, viable and achievable as a means of supporting:”
Decision making on the project’s (continued) investment is the correct option.Incorrect
According to the theme statement described follow:
“The theme of the Business Case is to create frameworks for deciding whether the project is (and remains) attractive, viable and achievable as a means of supporting:”
Decision making on the project’s (continued) investment is the correct option. -
Question 2 of 30
2. Question
If the Project Board has accepted the Business Case as part of the Project Initiation Documentation (PID), when is it needed to be updated?
Correct
As part of the Managing a Stage Boundary process, the Business Case is regularly updated so that the Project Board can have the very latest forecasts available for its decision on whether to approve the next step.
Incorrect
As part of the Managing a Stage Boundary process, the Business Case is regularly updated so that the Project Board can have the very latest forecasts available for its decision on whether to approve the next step.
-
Question 3 of 30
3. Question
The business case is a time scale. What does it mean by this time scale?
Correct
It is found that the project time scale and the period during which benefits will be realized.
Incorrect
It is found that the project time scale and the period during which benefits will be realized.
-
Question 4 of 30
4. Question
In which process is the Benefits Review Plan created?
Correct
The plan is created during Initiation at the same time as the Business Case is worked up into full detail.
Incorrect
The plan is created during Initiation at the same time as the Business Case is worked up into full detail.
-
Question 5 of 30
5. Question
Who is responsible for identifying and recognizing the advantages of using goods in PRINCE2?
Correct
The Senior Consumer represents those who will use the deliverables (products) of the project and continue to produce benefits including increased revenue and cost savings.
Incorrect
The Senior Consumer represents those who will use the deliverables (products) of the project and continue to produce benefits including increased revenue and cost savings.
-
Question 6 of 30
6. Question
Which of these positions can’t be shared and only one person must fill-in?
Correct
It is to be noted that PRINCE2 allows only one, Project Manager.
Incorrect
It is to be noted that PRINCE2 allows only one, Project Manager.
-
Question 7 of 30
7. Question
What functions of the Project Board devote personnel resources to the project?
Correct
The Senior Supplier authorizes specialist tools, and every customer tool is approved by the Senior Customer (such as helping to define specifications and participating in testing).
Incorrect
The Senior Supplier authorizes specialist tools, and every customer tool is approved by the Senior Customer (such as helping to define specifications and participating in testing).
-
Question 8 of 30
8. Question
What of these functions is optional, and in a PRINCE2 project need not be filled out?
Correct
The Project Manager will handle the job, usually in a small project.
Incorrect
The Project Manager will handle the job, usually in a small project.
-
Question 9 of 30
9. Question
Which of these positions does not form part of the project management team at PRINCE2?
Correct
It is found that quality Assurance is an external, organizational feature of the project.
Incorrect
It is found that quality Assurance is an external, organizational feature of the project.
-
Question 10 of 30
10. Question
Which of these is not an acceptable set of roles to be covered in a PRINCE2 project by a single person?
Correct
Plan Monitoring must be Plan Manager-independent. It’s perfect for one person to be the Project Board on a very small project, and to fill all three board positions.
Incorrect
Plan Monitoring must be Plan Manager-independent. It’s perfect for one person to be the Project Board on a very small project, and to fill all three board positions.
-
Question 11 of 30
11. Question
Which of these isdoes not contribute to be a part of Project Initiation Documents (PID)?
Correct
Phase schedule for step one of production. The PID contains the Business Case, Project Plan, and Risk Management Policy. The Stage Plan is different, as it is not a ‘whole project’ – typically there are a number of Stage Plans since most projects are multi-stage – and the Project Initiation Report (PID) covers the whole project.
Incorrect
Phase schedule for step one of production. The PID contains the Business Case, Project Plan, and Risk Management Policy. The Stage Plan is different, as it is not a ‘whole project’ – typically there are a number of Stage Plans since most projects are multi-stage – and the Project Initiation Report (PID) covers the whole project.
-
Question 12 of 30
12. Question
When a team manager receives a progress update from Project Managers, what do they do?
Correct
It should be noted that a team’s progress details will be fed into the Stage Plan.
Incorrect
It should be noted that a team’s progress details will be fed into the Stage Plan.
-
Question 13 of 30
13. Question
If a team member reports a real new risk to the Project Manager what the first step will the Project Manager take?
Correct
“Capture” risks is essential, and that’s part of the Risk Register feature. It is doubtful that complete information will still be available – such as how to handle the risk – but this will not stop the Project Manager from setting up the application, which can be augmented with more details when they become available.
Incorrect
“Capture” risks is essential, and that’s part of the Risk Register feature. It is doubtful that complete information will still be available – such as how to handle the risk – but this will not stop the Project Manager from setting up the application, which can be augmented with more details when they become available.
-
Question 14 of 30
14. Question
When the stage is expected to go just very marginally beyond cost tolerance of the stage (the plus and minus amounts set by the Project Board), but this does not impact cost tolerance of the project, what will the Project Manager do?
Correct
The Project Manager has no choice but to refer the matter to the Board and do so without hesitation. The tolerances are a strict order from the Project Board – the ‘boss’ of the Project Manager – that should the estimates go beyond the specified limits, then the board must be immediately told.
Incorrect
The Project Manager has no choice but to refer the matter to the Board and do so without hesitation. The tolerances are a strict order from the Project Board – the ‘boss’ of the Project Manager – that should the estimates go beyond the specified limits, then the board must be immediately told.
-
Question 15 of 30
15. Question
What PRINCE2 operation does a Project Manager conduct before taking action to correct a stage that has deviated from its strategy, or before escalating specifics of that deviation to the Project Board?
Correct
This is a test to see ‘where we are now’ before determining if the action falls under the delegated authority of the Project Manager. Have a look at Figure 7.1 earlier in this chapter if you are not clear on that point.
Incorrect
This is a test to see ‘where we are now’ before determining if the action falls under the delegated authority of the Project Manager. Have a look at Figure 7.1 earlier in this chapter if you are not clear on that point.
-
Question 16 of 30
16. Question
The Project Manager updates the Stage Plan when conducting the task ‘Check Job Package Status.’ What’s that for?
Correct
To serve some useful purpose in managing the stage, the Stage Plan must be kept up-to-date, and therefore actuals are entered when this information arrives from Team Managers in or followed by Checkpoint Reports. [Manual 15.4.2 last bullet point, P2FD Ch7 Managing workflow to teams-Testing job package progress]
Incorrect
To serve some useful purpose in managing the stage, the Stage Plan must be kept up-to-date, and therefore actuals are entered when this information arrives from Team Managers in or followed by Checkpoint Reports. [Manual 15.4.2 last bullet point, P2FD Ch7 Managing workflow to teams-Testing job package progress]
-
Question 17 of 30
17. Question
The team discovered damaged wood during the first stage of distribution which will need repair first.
What one alternative properly represents, or lacks, action to update the Project Plan?Correct
The ‘legal’ and so right response to the exam is that the Project Plan should be revised at the stage boundaries, not in the Controlling a Stage phase, which is the focus of this section. This is likely to be different in reality, but this problem is partly to highlight the point that the exams are based on PRINCE2 as set out in the manual.
Incorrect
The ‘legal’ and so right response to the exam is that the Project Plan should be revised at the stage boundaries, not in the Controlling a Stage phase, which is the focus of this section. This is likely to be different in reality, but this problem is partly to highlight the point that the exams are based on PRINCE2 as set out in the manual.
-
Question 18 of 30
18. Question
At the start of the first production process, a team leader found a faster way to do some planning work on the walls and ceilings of the offices, without the efficiency, and suggested this on a matter. What 1 step the Project Manager will take?
Correct
The Project Manager should record the issue one way or the other (register or log) and then
check it out. It shouldn’t be ignored or passed to a Project Board member. Neither should a
Project Manager sends it straight back and tells the team member to get on with it. What if the
team member was wrong? At the very least, the Project Manager would be likely to talk to the
Team Manager about the issue, as part of the ‘examine’ function of the activity ‘Capture and
examine issues and risks’.Incorrect
The Project Manager should record the issue one way or the other (register or log) and then
check it out. It shouldn’t be ignored or passed to a Project Board member. Neither should a
Project Manager sends it straight back and tells the team member to get on with it. What if the
team member was wrong? At the very least, the Project Manager would be likely to talk to the
Team Manager about the issue, as part of the ‘examine’ function of the activity ‘Capture and
examine issues and risks’. -
Question 19 of 30
19. Question
Which of the following options names plans that are generated during the Initiating a Project process?
Correct
On stage boundary, just before that stage begins, a Stage Plan is formed. Stage Plans during Initiation are not produced en bloc for the whole project. There is no such thing as the PRINCE2 Business Strategy. A Team Plan is created when a Team Manager receives a Work Package (assignment) during a distribution point, not during implementation, as necessary.
Incorrect
On stage boundary, just before that stage begins, a Stage Plan is formed. Stage Plans during Initiation are not produced en bloc for the whole project. There is no such thing as the PRINCE2 Business Strategy. A Team Plan is created when a Team Manager receives a Work Package (assignment) during a distribution point, not during implementation, as necessary.
-
Question 20 of 30
20. Question
Whose function is responsible for creating the documentation for the initiation of the project (PID)?
Correct
It should be kept in mind that when generating the PID, the Project Manager consults with others but is responsible for that.
Incorrect
It should be kept in mind that when generating the PID, the Project Manager consults with others but is responsible for that.
-
Question 21 of 30
21. Question
What statements are a specified objective of the Controlling a Stage process?
Correct
It is to be noted that the purpose of the process Controlling a Stage is given following:
A. Report progress to the Project Board
B. Deal with issues
C. Assign work to be doneIncorrect
It is to be noted that the purpose of the process Controlling a Stage is given following:
A. Report progress to the Project Board
B. Deal with issues
C. Assign work to be done -
Question 22 of 30
22. Question
Which of the following helps to report the progress on the Work Package?
Correct
It is to be noted the checkpoint report is responsible for reporting the progress on the work package.
Incorrect
It is to be noted the checkpoint report is responsible for reporting the progress on the work package.
-
Question 23 of 30
23. Question
Which of the following is true about the highlight report?
Correct
It is described that,
The Highlight Report – the progress report produced by the Project Manager on a regular, timed basis and sent to the Project Board and any others who need to see it, as set down in the Communications Management Strategy.Incorrect
It is described that,
The Highlight Report – the progress report produced by the Project Manager on a regular, timed basis and sent to the Project Board and any others who need to see it, as set down in the Communications Management Strategy. -
Question 24 of 30
24. Question
Which of the following is not true about the work package?
Correct
Thus, the Work Package is both an order and an authority to create a single product, or even two or three products, on which working together makes sense. The Work Package will specify that there are three products involved, and it will include copies of the three Product Descriptions.
Incorrect
Thus, the Work Package is both an order and an authority to create a single product, or even two or three products, on which working together makes sense. The Work Package will specify that there are three products involved, and it will include copies of the three Product Descriptions.
-
Question 25 of 30
25. Question
Which is true about the work packages?
Correct
It is found that the Work Packages are the instruction pack asking a Team Manager to build a product, or more than one if it makes sense to do them together.
Incorrect
It is found that the Work Packages are the instruction pack asking a Team Manager to build a product, or more than one if it makes sense to do them together.
-
Question 26 of 30
26. Question
The Work Package function to specify the interface between which of the following?
Correct
The role of the Work Package to define the interface between Stage Controlling and Product Delivery Management. In other words, how it sets out the way the team manager and project manager should work together when a specific part of the job is being completed, such as the progress monitoring criteria.
Incorrect
The role of the Work Package to define the interface between Stage Controlling and Product Delivery Management. In other words, how it sets out the way the team manager and project manager should work together when a specific part of the job is being completed, such as the progress monitoring criteria.
-
Question 27 of 30
27. Question
Controlling the flow of work out to project teams does not require which of the following?
Correct
Controlling the flow of work out to project teams:
• Giving out work assignments (Work Packages) to Team Managers.
• Checking progress on the Work Packages.
• Getting the work back when it’s finished.Incorrect
Controlling the flow of work out to project teams:
• Giving out work assignments (Work Packages) to Team Managers.
• Checking progress on the Work Packages.
• Getting the work back when it’s finished. -
Question 28 of 30
28. Question
Who is responsible for identifying and recognizing the advantages of using goods in PRINCE2?
Correct
The Senior Consumer represents those who will use the deliverables (products) of the project and continue to produce benefits including increased revenue and cost savings.
Incorrect
The Senior Consumer represents those who will use the deliverables (products) of the project and continue to produce benefits including increased revenue and cost savings.
-
Question 29 of 30
29. Question
Which of these positions does not form part of the project management team at PRINCE2?
Correct
It is found that quality Assurance is an external, organizational feature of the project.
Incorrect
It is found that quality Assurance is an external, organizational feature of the project.
-
Question 30 of 30
30. Question
Who is responsible for the Communications Planning Policy preparations?
Correct
It is found that the Project Manager is the one responsible for the preparations of the Communication Management Strategy.
Incorrect