Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
Certdemy Premium Access
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 10 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
It is always very beneficial to involve all members of the project team in the initial decisions while implementing the PRINCE2 Agile. Which one of these is not the result of involving all the members of the project team?
Correct
Involving all members of the project team in these initial decisions creates an environment of high communication, transparency, empowerment, and ownership.
Incorrect
Involving all members of the project team in these initial decisions creates an environment of high communication, transparency, empowerment, and ownership.
-
Question 2 of 10
2. Question
Involving all members of the project team in the initial decisions creates an environment of high communication, transparency, empowerment, and ownership that carries forward throughout the project delivery. What does this make imply?
Correct
Involving all members of the project team in the initial decisions creates an environment of high communication, transparency, empowerment, and ownership that carries forward throughout the project delivery, leveraging one of the most powerful advantages of the PRINCE2 Agile framework.
Incorrect
Involving all members of the project team in the initial decisions creates an environment of high communication, transparency, empowerment, and ownership that carries forward throughout the project delivery, leveraging one of the most powerful advantages of the PRINCE2 Agile framework.
-
Question 3 of 10
3. Question
Once the core project team members are identified in setting a project in the PRINCE2 Agile, there are two steps expected to follow. One is to identify the most effective team structure and roles. What is the other step?
Correct
Once you have identified the core project team members, the next step is to identify the most effective team structure and roles – and to decide if there are additional people that need to be added to the project team.
Incorrect
Once you have identified the core project team members, the next step is to identify the most effective team structure and roles – and to decide if there are additional people that need to be added to the project team.
-
Question 4 of 10
4. Question
Under identifying the right project team, there are four steps that are very essential. Which one of these is not one of the steps in identifying the right project team?
Correct
Once the core project team members are identified, the next step is to identify the most effective team structure and roles – and to decide if there are additional people that need to be added to the project team. This includes:
1. Determining if there are people needed on the Project Board in addition to the executive, the senior user(s), and senior supplier(s) – and what their respective responsibilities will be.
2. Determining who is needed to accurately represent the full requirements for the project deliverables in addition to the senior user identifying their respective responsibilities and how they will interact with each other to confirm accuracy and consistency.
3. Determining whether the project requires a separately assigned team manager or whether the project manager (or, for Scrum projects, the Scrummaster) will effectively function in this role.
4. Determining the respective roles on the project delivery team, based on the Agile method selected (if it is known at this point in the process).Incorrect
Once the core project team members are identified, the next step is to identify the most effective team structure and roles – and to decide if there are additional people that need to be added to the project team. This includes:
1. Determining if there are people needed on the Project Board in addition to the executive, the senior user(s), and senior supplier(s) – and what their respective responsibilities will be.
2. Determining who is needed to accurately represent the full requirements for the project deliverables in addition to the senior user identifying their respective responsibilities and how they will interact with each other to confirm accuracy and consistency.
3. Determining whether the project requires a separately assigned team manager or whether the project manager (or, for Scrum projects, the Scrummaster) will effectively function in this role.
4. Determining the respective roles on the project delivery team, based on the Agile method selected (if it is known at this point in the process). -
Question 5 of 10
5. Question
In identifying the core project team members and their respective roles, one is expected to do it for a greater purpose. What would the outcome of these decisions require?
Correct
The outcome from these decisions may require the team to review and adjust the staff that was originally identified for the core project team, and to include these additional people in the ongoing planning discussions, where possible.
Incorrect
The outcome from these decisions may require the team to review and adjust the staff that was originally identified for the core project team, and to include these additional people in the ongoing planning discussions, where possible.
-
Question 6 of 10
6. Question
Once the project team is identified, what is important to ensure to achieve the proposed objectives?
Correct
Once the project team is identified, it is important to ensure that everyone on the team has a shared vision of what the project is intended to deliver and how the PRINCE2 Agile principles and practices will be implemented to achieve these objectives.
Incorrect
Once the project team is identified, it is important to ensure that everyone on the team has a shared vision of what the project is intended to deliver and how the PRINCE2 Agile principles and practices will be implemented to achieve these objectives.
-
Question 7 of 10
7. Question
In determining who is needed to accurately represent the full requirements for the project deliverables in addition to the senior user, which one of these is not inclusive following the identification of their respective responsibilities and how they will interact with each other to confirm accuracy and consistency?
Correct
In determining who is needed to accurately represent the full requirements for the project deliverables in addition to the senior user, including customer subject matter expert(s), product owner(s), business ambassador(s), business analyst(s), and requirements engineers(s) – identifying their respective responsibilities and how they will interact with each other to confirm accuracy and consistency
Incorrect
In determining who is needed to accurately represent the full requirements for the project deliverables in addition to the senior user, including customer subject matter expert(s), product owner(s), business ambassador(s), business analyst(s), and requirements engineers(s) – identifying their respective responsibilities and how they will interact with each other to confirm accuracy and consistency
-
Question 8 of 10
8. Question
When it is the first project that the team is delivering with PRINCE2 Agile regardless if they have experience of PRINCE2 projects before, what is strongly recommended to establish a shared understanding of PRINCE2 Agile and to set the focus for the ongoing project work?
Correct
If this is the first project that this team is delivering with PRINCE2 Agile (even if they have worked on PRINCE2 projects before), it is strongly recommended that all project participants – including the members of the Project Board, the project manager, and the project delivery team – get together for an interactive workshop to establish a shared understanding of PRINCE2 Agile and to set the focus for ongoing work.
Incorrect
If this is the first project that this team is delivering with PRINCE2 Agile (even if they have worked on PRINCE2 projects before), it is strongly recommended that all project participants – including the members of the Project Board, the project manager, and the project delivery team – get together for an interactive workshop to establish a shared understanding of PRINCE2 Agile and to set the focus for ongoing work.
-
Question 9 of 10
9. Question
As it is strongly recommended that all project participants – including the members of the Project Board, the project manager, and the project delivery team – get together for an interactive workshop to establish a shared understanding of PRINCE2 Agile and to set the focus for ongoing work, in what ways can this be done?
Correct
This can be done either as a separate session or as the first part of the project planning session(s)
Incorrect
This can be done either as a separate session or as the first part of the project planning session(s)
-
Question 10 of 10
10. Question
Immediately there is a common understanding of PRINCE2 Agile by the team, what should the workshop session(s) focus on?
Correct
Once the team has a common understanding of PRINCE2 Agile, the workshop session(s) should focus on establishing a shared vision of the key project information
Incorrect
Once the team has a common understanding of PRINCE2 Agile, the workshop session(s) should focus on establishing a shared vision of the key project information