Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
Certdemy Premium Access
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 10 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
The Project board mainly is responsible for the overarching management of the project. Several individuals make up the project board. Who are the members that make up the project board?
Correct
The Project Board is the project group responsible for the overarching management of the project and ensuring that the project continues to deliver its prospected business value for the organization.
Incorrect
The Project Board is the project group responsible for the overarching management of the project and ensuring that the project continues to deliver its prospected business value for the organization.
-
Question 2 of 10
2. Question
One of the important member of the project board is the senior supplier. What does this senior supplier represent?
Correct
The internal and external teams that ensure that the desired output is delivered make up the senior suppliers.
Incorrect
The internal and external teams that ensure that the desired output is delivered make up the senior suppliers.
-
Question 3 of 10
3. Question
The project board is very important to the makeup of the project requirements. What likely is this group of senior management responsible for?
Correct
The overarching management and ensuring the continuous delivery of business value to the organization is the sole responsibility of the project board.
Incorrect
The overarching management and ensuring the continuous delivery of business value to the organization is the sole responsibility of the project board.
-
Question 4 of 10
4. Question
The project board is made up of the executive, senior user and senior managers with other minor personalities. What likely is the executive in the makeup of the project board responsible for?
Correct
The Project Board as a group is responsible for the overarching management of the project and ensuring that the project is continuing to deliver its intended business value for the organization
Incorrect
The Project Board as a group is responsible for the overarching management of the project and ensuring that the project is continuing to deliver its intended business value for the organization
-
Question 5 of 10
5. Question
What is the responsibility of the senior user as a member of the project board?
Correct
The Senior User on the project board is responsible to protect the interest of the target audience that will be using the outputs from the project work and are responsible for making key decisions regarding the capabilities that the project team delivers.
Incorrect
The Senior User on the project board is responsible to protect the interest of the target audience that will be using the outputs from the project work and are responsible for making key decisions regarding the capabilities that the project team delivers.
-
Question 6 of 10
6. Question
The project manager is the link between the management and the project delivery team. What best describes the responsibility of the project manager?
Correct
The project manager is responsible for project delivery in accordance with the terms established by the project board.
Incorrect
The project manager is responsible for project delivery in accordance with the terms established by the project board.
-
Question 7 of 10
7. Question
The project manager is levied with various responsibilities. Which one is not inclusive of the responsibilities of the project manager?
Correct
The project manager aside ensuring project delivery in accordance with the directives of the project board allocates work, manages issues and risks, provide status updates, monitor time, budgets, scope, benefit, and quality tolerance and raising exceptions.
Incorrect
The project manager aside ensuring project delivery in accordance with the directives of the project board allocates work, manages issues and risks, provide status updates, monitor time, budgets, scope, benefit, and quality tolerance and raising exceptions.
-
Question 8 of 10
8. Question
Aside the major responsibilities of the project board in the PRINCE2, there are roles pushed to minor individuals also important to the realizing of the required business value. Who is importantly given a role as identified in the PRINCE2?
Correct
The roles identified in the PRINCE2 are the project board (the executive, the senior user, and the senior supplier), the project manager, and the team manager amongst others.
Incorrect
The roles identified in the PRINCE2 are the project board (the executive, the senior user, and the senior supplier), the project manager, and the team manager amongst others.
-
Question 9 of 10
9. Question
Artifacts are documents needed to be developed in PRINCE2 to authorize the project to begin and ensure effective ongoing project management. Which one is not an identified artifact of PRINCE2?
Correct
There are artifacts that need to be developed to authorize the project to begin and ensure the effective ongoing project management aside from the principles, themes, processes, and roles of PRINCE2 and they include project brief, the project initiation documentation (PID), the project product description, the benefits review plan, stage plans, highlight reports, checkpoint reports, exception reports, the configuration item record, the issue register, and the risk register.
Incorrect
There are artifacts that need to be developed to authorize the project to begin and ensure the effective ongoing project management aside from the principles, themes, processes, and roles of PRINCE2 and they include project brief, the project initiation documentation (PID), the project product description, the benefits review plan, stage plans, highlight reports, checkpoint reports, exception reports, the configuration item record, the issue register, and the risk register.
-
Question 10 of 10
10. Question
There are three levels of PRINCE2 knowledge from a structured PRINCE2 qualification scheme to ensure the effective execution of PRINCE2. What are the three levels?
Correct
These levels of knowledge ensure that PRINCE2 is effectively executed in the globally recognized qualification scheme from the structured PRINCE2
Incorrect
These levels of knowledge ensure that PRINCE2 is effectively executed in the globally recognized qualification scheme from the structured PRINCE2