Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
Certdemy Premium Access
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 10 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
Which of these is not the benefit of using PRINCE2 Agile?
Correct
PRINCE2 Agile is a framework that aligns the independent PRINCE2 and Agile frameworks thereby providing greater management visibility and support. It is a tool that corrects the deficiencies in either PRINCE2 or Agile frameworks on an individual basis.
Incorrect
PRINCE2 Agile is a framework that aligns the independent PRINCE2 and Agile frameworks thereby providing greater management visibility and support. It is a tool that corrects the deficiencies in either PRINCE2 or Agile frameworks on an individual basis.
-
Question 2 of 10
2. Question
What high-value communication tools does PRINCE2 Agile project use?
Correct
This communication tool enables the Board members to know the status of the project work in this era of ever-changing technologies. This helps them to be very responsive as regards maintaining their business value and retaining their partners or clients as the case may be. It is an essential tool.
Incorrect
This communication tool enables the Board members to know the status of the project work in this era of ever-changing technologies. This helps them to be very responsive as regards maintaining their business value and retaining their partners or clients as the case may be. It is an essential tool.
-
Question 3 of 10
3. Question
Projects in controlled environments are based on the understanding that well-managed projects needs but?
Correct
PRINCE2 provides the senior management with the assurance that their funded projects are producing the expected level of business value. The tool is so perfect for governance but at the same time lacks some artifacts that need to be developed to enable the start of the project and ensure effective ongoing project management.
Incorrect
PRINCE2 provides the senior management with the assurance that their funded projects are producing the expected level of business value. The tool is so perfect for governance but at the same time lacks some artifacts that need to be developed to enable the start of the project and ensure effective ongoing project management.
-
Question 4 of 10
4. Question
PRINCE2 Agile combines the management ongoing need for business value confirmation and due diligence with the empowerment and flexibility that the project team needs to deliver the required outcomes which include but?
Correct
PRINCE2 Agile combines PRINCE2 and Agile frameworks in such a way that both maintain the basis of PRINCE2 method essentials and delivers the efficiencies and core values of the Agile method.
Incorrect
PRINCE2 Agile combines PRINCE2 and Agile frameworks in such a way that both maintain the basis of PRINCE2 method essentials and delivers the efficiencies and core values of the Agile method.
-
Question 5 of 10
5. Question
PRINCE2 Agile is ‘Agile agnostic’ because
Correct
PRINCE2 Agile is “Agile agnostic,” and are best suited for organization and projects. PRINCE2 Agile achieves the integrated approach of well-managed business outcomes with high-level productivity and value-driven focus by developing necessary requirements for projects to adhere to thereby enabling the flexibility to ascertain roles, processes, and artifacts needed specifically for each project.
Incorrect
PRINCE2 Agile is “Agile agnostic,” and are best suited for organization and projects. PRINCE2 Agile achieves the integrated approach of well-managed business outcomes with high-level productivity and value-driven focus by developing necessary requirements for projects to adhere to thereby enabling the flexibility to ascertain roles, processes, and artifacts needed specifically for each project.
-
Question 6 of 10
6. Question
To implement the necessary principles of the PRINCE2 framework, one of these is not needed
Correct
The PRINCE2 framework also defines specific project roles and responsibilities that are necessary. Though the framework seems more like having PRINCE2 and Agile methods working concurrently but the principles of PRINCE2 Agile makes the approach very powerful. To implement the necessary principles, the following authorities: the executive who represents the senior management interest, the senior users who represent the target audience, and the senior suppliers who represent the external and internal team delivering the required outputs, are so needed to foster understanding, application, and productivity.
Incorrect
The PRINCE2 framework also defines specific project roles and responsibilities that are necessary. Though the framework seems more like having PRINCE2 and Agile methods working concurrently but the principles of PRINCE2 Agile makes the approach very powerful. To implement the necessary principles, the following authorities: the executive who represents the senior management interest, the senior users who represent the target audience, and the senior suppliers who represent the external and internal team delivering the required outputs, are so needed to foster understanding, application, and productivity.
-
Question 7 of 10
7. Question
The following are inclusive in the seven processes that comprise the full life cycle in PRINCE2 projects except
Correct
Seven processes that comprise the full project lifecycle of the PRINCE2 method are: starting up a project, directing a project, initiating a project, controlling a stage, managing product delivery, managing stage boundaries, and closing a project. All of which are adaptable to suit the method.
Incorrect
Seven processes that comprise the full project lifecycle of the PRINCE2 method are: starting up a project, directing a project, initiating a project, controlling a stage, managing product delivery, managing stage boundaries, and closing a project. All of which are adaptable to suit the method.
-
Question 8 of 10
8. Question
How many principles guide all the project work in the PRINCE2 framework?
Correct
Seven principles guide all of the project work in the PRINCE2 framework. These principles help the PRINCE2 achieves its objectives.
Incorrect
Seven principles guide all of the project work in the PRINCE2 framework. These principles help the PRINCE2 achieves its objectives.
-
Question 9 of 10
9. Question
Which of the following doesn’t represent the method that allows PRINCE2 and Agile to work cohesively in a PRINCE2 Agile framework
Correct
There’s an important distinction in PRINCE2 Agile which is primarily the servant leadership roles where the project delivery team is directly responsible for managing their work, with the support of the project and team managers.
Incorrect
There’s an important distinction in PRINCE2 Agile which is primarily the servant leadership roles where the project delivery team is directly responsible for managing their work, with the support of the project and team managers.
-
Question 10 of 10
10. Question
PRINCE2 Agile seems to represent PRINCE2 and Agile working concurrently but PRINCE2 Agile is a powerful tool because of the following key principles except
Correct
PRINCE2 Agile fosters – and relies upon – an environment of transparency, collaboration, communication, exploration, self-organization, and accountability. The core principles are expanded in PRINCE2 Agile to be very inclusive.
Incorrect
PRINCE2 Agile fosters – and relies upon – an environment of transparency, collaboration, communication, exploration, self-organization, and accountability. The core principles are expanded in PRINCE2 Agile to be very inclusive.