Quiz-summary
0 of 30 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
Information
PRINCE2 – Agile Foundation Exam – Premium Access
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 30 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- Answered
- Review
-
Question 1 of 30
1. Question
What statement is false about PRINCE2’s business as usual?
Correct
Business as usual with PRINCE2 is any work that is a part of the normal operations of the organization. It does not have a predefined end. People from the same area of the business is involved. The work of the projects often leads to business-as-usual work. This business as usual with PRINCE2 doesn’t introduce major changes to the organization.
Incorrect
Business as usual with PRINCE2 is any work that is a part of the normal operations of the organization. It does not have a predefined end. People from the same area of the business is involved. The work of the projects often leads to business-as-usual work. This business as usual with PRINCE2 doesn’t introduce major changes to the organization.
-
Question 2 of 30
2. Question
What is not one of the main areas of project management?
Correct
Project management has four main areas:
(a) Plan
(b) Delegate
(c) Monitor
(d) ControlThese four areas exist to ensure that the work of the projects is all co-coordinated in the most effective way possible to consistently deliver the required results within the deadlines and budgets of the project.
Incorrect
Project management has four main areas:
(a) Plan
(b) Delegate
(c) Monitor
(d) ControlThese four areas exist to ensure that the work of the projects is all co-coordinated in the most effective way possible to consistently deliver the required results within the deadlines and budgets of the project.
-
Question 3 of 30
3. Question
Which of the following describes Delegate in relation to project management?
Correct
Delegate ensures that the people are doing their work at the correct time. It is not just people but having the right people doing the right work. Communication is the key to this main area. Statement 1 refers to Plan. Statement 3 refers to Monitor. Statement 4 refers to Control.
Incorrect
Delegate ensures that the people are doing their work at the correct time. It is not just people but having the right people doing the right work. Communication is the key to this main area. Statement 1 refers to Plan. Statement 3 refers to Monitor. Statement 4 refers to Control.
-
Question 4 of 30
4. Question
Which of the following describes Control in relation to project management?
Correct
Control involves getting the right activities done to create the right products. To create the right products, the timing of the activities must also be right. This also involves all of the work of all of the people involved in the project. Statement 2 refers to Monitor. Statement 3 and Statement 4 refers to Delegate.
Incorrect
Control involves getting the right activities done to create the right products. To create the right products, the timing of the activities must also be right. This also involves all of the work of all of the people involved in the project. Statement 2 refers to Monitor. Statement 3 and Statement 4 refers to Delegate.
-
Question 5 of 30
5. Question
Which of the following is not a statement about Plan in relation to project management?
Correct
The plan shows how a project should be done. The plan also shows what needs to be done. This stops unnecessary situations or inconveniences from happening. A good example of this is having renters moving into an unfinished house. It ensures that all work is effectively coordinated. Statement 4 refers to Delegate.
Incorrect
The plan shows how a project should be done. The plan also shows what needs to be done. This stops unnecessary situations or inconveniences from happening. A good example of this is having renters moving into an unfinished house. It ensures that all work is effectively coordinated. Statement 4 refers to Delegate.
-
Question 6 of 30
6. Question
Which of the following is not an area wherein a project’s performance can be measured?
Correct
These are areas that measure the performance of a project:
(a) Project’s cost
(b) Project’s timescale
(c) Project’s quality
(d) Project’s scope
(e) The risks involved in the project
(f) The benefits gained from the projectHow the project manager handles stress is not a part of the list.
Incorrect
These are areas that measure the performance of a project:
(a) Project’s cost
(b) Project’s timescale
(c) Project’s quality
(d) Project’s scope
(e) The risks involved in the project
(f) The benefits gained from the projectHow the project manager handles stress is not a part of the list.
-
Question 7 of 30
7. Question
Which of the following is one of the four main parts of PRINCE2?
Correct
The main parts of PRINCE2:
(a) Principles
(b) Themes
(c) Processes
(d) Project environmentThese main parts are referred to as the integrated elements. PRINCE2 provides a range of processes with the steps that ensure that the correct management activities are done.
Incorrect
The main parts of PRINCE2:
(a) Principles
(b) Themes
(c) Processes
(d) Project environmentThese main parts are referred to as the integrated elements. PRINCE2 provides a range of processes with the steps that ensure that the correct management activities are done.
-
Question 8 of 30
8. Question
Which of the following is not a part of the seven processes of PRINCE2?
Correct
These are the correct processes:
(a) Starting a project
(b) Directing a project
(c) Initiating a project
(d) Controlling a stage
(e) Management of product delivery
(f) Management of stage boundary
(g) Closing projectIncorrect
These are the correct processes:
(a) Starting a project
(b) Directing a project
(c) Initiating a project
(d) Controlling a stage
(e) Management of product delivery
(f) Management of stage boundary
(g) Closing project -
Question 9 of 30
9. Question
Which of the following best describes the process of controlling a stage in relation to the seven processes of PRINCE2?
Correct
Controlling a stage covers the day-to-day work of the project manager. The work involves activities such as reporting, delegating work to people, and dealing with various risks and issues. Statement 1 refers to Directing a project. Statement 2 refers to Initiating a project. Statement 4 refers to Managing product deliveries.
Incorrect
Controlling a stage covers the day-to-day work of the project manager. The work involves activities such as reporting, delegating work to people, and dealing with various risks and issues. Statement 1 refers to Directing a project. Statement 2 refers to Initiating a project. Statement 4 refers to Managing product deliveries.
-
Question 10 of 30
10. Question
Which of the following best describes managing a state boundary in relation to the seven processes of PRINCE2?
Correct
Managing a state boundary involves reporting the achievements of each stage. It also involves making a detailed plan for the next stage. Statement 1 and Statement 4 refers to Closing a project. Statement 3 refers to Starting up a project.
Incorrect
Managing a state boundary involves reporting the achievements of each stage. It also involves making a detailed plan for the next stage. Statement 1 and Statement 4 refers to Closing a project. Statement 3 refers to Starting up a project.
-
Question 11 of 30
11. Question
Which of the following is not a theme under PRINCE2?
Correct
These are the correct themes of PRINCE2:
(a) Organization
(b) Quality
(c) Plans
(d) Risk
(e) Change
(f) Business case
(g) ProgressThe purpose of themes is to describe how PRINCE2 would recommend carrying out different parts of the project.
Incorrect
These are the correct themes of PRINCE2:
(a) Organization
(b) Quality
(c) Plans
(d) Risk
(e) Change
(f) Business case
(g) ProgressThe purpose of themes is to describe how PRINCE2 would recommend carrying out different parts of the project.
-
Question 12 of 30
12. Question
Which of the following is not a part of the levels of hierarchy in the PRINCE2 project management structure?
Correct
These are the correct hierarchy levels in the project management of PRINCE2?
(a) Corporate, Program Management, or Customer
(b) Directing level
(c) Managing level
(d) Delivering level
There are other roles such as project assurance, project support, and change authority.Incorrect
These are the correct hierarchy levels in the project management of PRINCE2?
(a) Corporate, Program Management, or Customer
(b) Directing level
(c) Managing level
(d) Delivering level
There are other roles such as project assurance, project support, and change authority. -
Question 13 of 30
13. Question
Which of the following statements is false about Management products in PRINCE2?
Correct
These management products are products that help the project management team manage their project. Amendments are made to the new version of the document when updates are made.
There are three types of management products: baselines, records, and reports. The plan is an example of a baseline management product.Incorrect
These management products are products that help the project management team manage their project. Amendments are made to the new version of the document when updates are made.
There are three types of management products: baselines, records, and reports. The plan is an example of a baseline management product. -
Question 14 of 30
14. Question
Which of the following describes Baseline management products?
Correct
Baseline management products may involve going through multiple changes during the duration of the project. This may be used by the project team to see how the project has evolved. Statement 1 refers to records. Statement 3 and Statement 4 refer to reports.
Incorrect
Baseline management products may involve going through multiple changes during the duration of the project. This may be used by the project team to see how the project has evolved. Statement 1 refers to records. Statement 3 and Statement 4 refer to reports.
-
Question 15 of 30
15. Question
Which of the following is the correct benefits of using PRINCE2?
Correct
These are the correct benefits of PRINCE2:
(a) It is highly beneficial for projects.
(b) It is designed for any type of project.
(c) It can be modified to adapt to different projects.
(d) It provides a common vocabulary of project terms.
(e) It defines the responsibilities of project management.
(f) It focuses on what needs to be done.
(g) It ensures efficiency.
(h) It ensures that the projects provide value
(i) It allows people to improve their management skills.
(j) It provides a theoretical management framework.Incorrect
These are the correct benefits of PRINCE2:
(a) It is highly beneficial for projects.
(b) It is designed for any type of project.
(c) It can be modified to adapt to different projects.
(d) It provides a common vocabulary of project terms.
(e) It defines the responsibilities of project management.
(f) It focuses on what needs to be done.
(g) It ensures efficiency.
(h) It ensures that the projects provide value
(i) It allows people to improve their management skills.
(j) It provides a theoretical management framework. -
Question 16 of 30
16. Question
Which of the following statements is false about the principle: manage by stage?
Correct
Management stages are often called stages. Within a stage, a collection of products is created. The stages may be divided into time periods. Each stage of a project may last for years. This makes it easier for the project manager to look-over each stage. Once a stage is done the project manager will report to the board members who will then authorized the next stage.
Incorrect
Management stages are often called stages. Within a stage, a collection of products is created. The stages may be divided into time periods. Each stage of a project may last for years. This makes it easier for the project manager to look-over each stage. Once a stage is done the project manager will report to the board members who will then authorized the next stage.
-
Question 17 of 30
17. Question
Which of the following is false about management stages in a PRINCE2 project?
Correct
There are at least two stages in a PRINCE2 project. A planning stage, which is also called the initiation stage, and the stage where a specialist delivers a product are the two consistent stages in each project. Management stages help with planning and help senior managers who are a part of the project board. These members no longer need to get involved in day-to-day management.
Incorrect
There are at least two stages in a PRINCE2 project. A planning stage, which is also called the initiation stage, and the stage where a specialist delivers a product are the two consistent stages in each project. Management stages help with planning and help senior managers who are a part of the project board. These members no longer need to get involved in day-to-day management.
-
Question 18 of 30
18. Question
Which of the following is not an area where constraints can be set?
Correct
The following are the correct areas where constraint can be set:
(a) Time
(b) Cost
(c) Scope
(d) Quality
(e) Risk
(f) BenefitsDisadvantages is not one of the areas. Exceptions are for situations wherein a certain amount of leeway or tolerances are allowed around these constraints.
Incorrect
The following are the correct areas where constraint can be set:
(a) Time
(b) Cost
(c) Scope
(d) Quality
(e) Risk
(f) BenefitsDisadvantages is not one of the areas. Exceptions are for situations wherein a certain amount of leeway or tolerances are allowed around these constraints.
-
Question 19 of 30
19. Question
Which of the following statements is false about tailoring in PRINCE2 projects?
Correct
PRINCE2 may place some limits on how you tailor techniques. Each theme may be tailored by the project management theme. Applying PRINCE2 may reduce the risks to a certain project. It is said that it is mandatory to tailor the method. Tailoring doesn’t just include increasing or decreasing PRINCE2. It can also involve adapting the method.
Incorrect
PRINCE2 may place some limits on how you tailor techniques. Each theme may be tailored by the project management theme. Applying PRINCE2 may reduce the risks to a certain project. It is said that it is mandatory to tailor the method. Tailoring doesn’t just include increasing or decreasing PRINCE2. It can also involve adapting the method.
-
Question 20 of 30
20. Question
Which of the following is not on of the correct factors that may influence how PRINCE2 is tailored?
Correct
These are the correct factors that may influence how PRINCE2 is tailored:
(a) The project management team’s capabilities
(b) The Organization’s maturity
(c) Legal contracts
(d) The environment wherein the project is done in
(e) Whether or not there are pre-existing project management termsIncorrect
These are the correct factors that may influence how PRINCE2 is tailored:
(a) The project management team’s capabilities
(b) The Organization’s maturity
(c) Legal contracts
(d) The environment wherein the project is done in
(e) Whether or not there are pre-existing project management terms -
Question 21 of 30
21. Question
Which of the following is not an environment in PRINCE2 projects?
Correct
There are only three environments. Program environments is a big project. PRINCE2 can be used to manage individual projects within the program. Commercial Customer and Supplier Environment means a customer is always there and usually pays for the work and a supplier that always provides skills and resources. The agile environment is a collection of approaches in the software industry.
Incorrect
There are only three environments. Program environments is a big project. PRINCE2 can be used to manage individual projects within the program. Commercial Customer and Supplier Environment means a customer is always there and usually pays for the work and a supplier that always provides skills and resources. The agile environment is a collection of approaches in the software industry.
-
Question 22 of 30
22. Question
Which statement correctly describes sprints in relation to Agile Environment?
Correct
Sprints are iterations that are quite short. These may last around three to four weeks. Statement 2 refers to failing fast. Statement 3 refers to Timeboxing. Statement 4 refers to the backlog. The list of requirements stated is given by the customer. Agile environment prefers to call these requirements user stories.
Incorrect
Sprints are iterations that are quite short. These may last around three to four weeks. Statement 2 refers to failing fast. Statement 3 refers to Timeboxing. Statement 4 refers to the backlog. The list of requirements stated is given by the customer. Agile environment prefers to call these requirements user stories.
-
Question 23 of 30
23. Question
Which of the following statements is false about the roles from Scrum agile approach?
Correct
There are two rules from the Scrum agile approach. The roles regularly used are the scrum master and the product owner. The scrum master leads the scrum delivery team. The product owner does not lead a scrum delivery team but it does represent the customer. Product owners also collate the user stories that are required for certain products
Incorrect
There are two rules from the Scrum agile approach. The roles regularly used are the scrum master and the product owner. The scrum master leads the scrum delivery team. The product owner does not lead a scrum delivery team but it does represent the customer. Product owners also collate the user stories that are required for certain products
-
Question 24 of 30
24. Question
Which of the following correctly describes the project brief?
Correct
A product brief is a result of mandating the project, expanding the information to provide details to form a solid basis for a decision of whether or not to commission a project. This is the output of the work that goes into a new management product. Product brief is not a role in scrum agile approach. Statement 2 refers to the Initiation stage. Statement 3 refers to authorized initiation.
Incorrect
A product brief is a result of mandating the project, expanding the information to provide details to form a solid basis for a decision of whether or not to commission a project. This is the output of the work that goes into a new management product. Product brief is not a role in scrum agile approach. Statement 2 refers to the Initiation stage. Statement 3 refers to authorized initiation.
-
Question 25 of 30
25. Question
What is true about the step of starting up a project?
Correct
Appointing a senior-level person to the executive role is the first step for this. Corporate, program management and the customer is allowed to appoint a senior-level person to this role. The person who takes up the role must act as the key decision-maker for the project.
Incorrect
Appointing a senior-level person to the executive role is the first step for this. Corporate, program management and the customer is allowed to appoint a senior-level person to this role. The person who takes up the role must act as the key decision-maker for the project.
-
Question 26 of 30
26. Question
What statement is true about project mandate in PRINCE2?
Correct
The project mandate answers what, why, when, where, who, and how questions of the project. Creating a project mandate must happen before the project starts. A person or a group of people are assigned to do this. The first set of activities may be all about refining the details of the project or checking if the first set of activities are correct at one time.
Incorrect
The project mandate answers what, why, when, where, who, and how questions of the project. Creating a project mandate must happen before the project starts. A person or a group of people are assigned to do this. The first set of activities may be all about refining the details of the project or checking if the first set of activities are correct at one time.
-
Question 27 of 30
27. Question
Which is not a stage of PRINCE2 process model?
Correct
There are four different stages of the PRINCE2 process model:
(a) Pre-project – It asks what happens before the project.
(b) Initiation stage – It asks what happens at the start of the project.
(c) Subsequent delivery stage – It asks what happens in the middle of the project.
(d) Final delivery – It asks what happens at the end of the project.Incorrect
There are four different stages of the PRINCE2 process model:
(a) Pre-project – It asks what happens before the project.
(b) Initiation stage – It asks what happens at the start of the project.
(c) Subsequent delivery stage – It asks what happens in the middle of the project.
(d) Final delivery – It asks what happens at the end of the project. -
Question 28 of 30
28. Question
Which of the following principles of the agile approach is false in relation to their value?
Correct
These are the correct principle of the agile approach:
(a) Individuals and interactions > Process and tools
(b) Working products > Comprehensive documentation
(c) Customer collaboration > Contract negotiation
(d) Responding to change > Following the planAgile approaches deliver their products over a series of iterations, not all at the end of the project.
Incorrect
These are the correct principle of the agile approach:
(a) Individuals and interactions > Process and tools
(b) Working products > Comprehensive documentation
(c) Customer collaboration > Contract negotiation
(d) Responding to change > Following the planAgile approaches deliver their products over a series of iterations, not all at the end of the project.
-
Question 29 of 30
29. Question
What information is not included in the PID?
Correct
These are included in the PID
(a) Project Plan
(b) Approach documents
(c) Business case’s details
(d) The project management team’s information
(e) Project approach details
(f) Project definition
(g) Information on how the project will be controlled and how PRINCE2 will be tailoredIncorrect
These are included in the PID
(a) Project Plan
(b) Approach documents
(c) Business case’s details
(d) The project management team’s information
(e) Project approach details
(f) Project definition
(g) Information on how the project will be controlled and how PRINCE2 will be tailored -
Question 30 of 30
30. Question
Which of the following is not included in the project definition in relation to PID?
Correct
These are included in the project definition:
(a) Background of the project
(b) Objectives of the project
(c) The scope of the projectMonitoring the progress of the project is under information on how the information will be controlled. This also includes the reports required for this information.
Incorrect
These are included in the project definition:
(a) Background of the project
(b) Objectives of the project
(c) The scope of the projectMonitoring the progress of the project is under information on how the information will be controlled. This also includes the reports required for this information.