Quiz-summary
0 of 30 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
Information
PRINCE2 – Agile Foundation Exam – Premium Access
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 30 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- Answered
- Review
-
Question 1 of 30
1. Question
Which of the following is an incorrect step of PRINCE2?
Correct
These are the correct steps:
Step 1: Creating a Project Mandate
Step 2: Appoint an Executive
Step 3: Appoint a Project Manager
Step 4: Create the project brief and recruit the project management team
Step 5: Authorize Initiation
Step 6: Create Project initiation documentation
Step 7: Create a plan for the first delivery stage
Step 8: Authorize project and first step delivery
Step 9: Manage delivery stage
Step 10: Create Stage Specialist Products
Step 11: Plan next stage
Step 12: Authorize another delivery
Step 13: Manage the final stage
Step 14: Create specialist products for the final stage
Step 15: Prepare the end of the projectIncorrect
These are the correct steps:
Step 1: Creating a Project Mandate
Step 2: Appoint an Executive
Step 3: Appoint a Project Manager
Step 4: Create the project brief and recruit the project management team
Step 5: Authorize Initiation
Step 6: Create Project initiation documentation
Step 7: Create a plan for the first delivery stage
Step 8: Authorize project and first step delivery
Step 9: Manage delivery stage
Step 10: Create Stage Specialist Products
Step 11: Plan next stage
Step 12: Authorize another delivery
Step 13: Manage the final stage
Step 14: Create specialist products for the final stage
Step 15: Prepare the end of the project -
Question 2 of 30
2. Question
Which of the following is not an action done by the project manager?
Correct
These are actions done by the project manager:
(a) Preparing the end of the project
(b) Managing the final delivery stage
(c) Planning the next stage
(d) Managing the delivery stage
(e) Creating a plan for the first delivery stage
(f) Creating the project initiation projectIncorrect
These are actions done by the project manager:
(a) Preparing the end of the project
(b) Managing the final delivery stage
(c) Planning the next stage
(d) Managing the delivery stage
(e) Creating a plan for the first delivery stage
(f) Creating the project initiation project -
Question 3 of 30
3. Question
What is not a basic responsibility of the Executive?
Correct
These are the basic responsibilities of the Executive:
(a) Appointing the Project Manager
(b) Being the key-decision maker of the project
(c) Creating the project briefIncorrect
These are the basic responsibilities of the Executive:
(a) Appointing the Project Manager
(b) Being the key-decision maker of the project
(c) Creating the project brief -
Question 4 of 30
4. Question
What activities are carried out during the managing product delivery process?
Correct
These are the correct activities done during this process:
(a) Accepting the project manager’s work
(b) Creating specialist products
(c) Delivering the specialist products to the project managerThese activities are carried out by the team managers and their teams. Teams regularly report the progress of their work via creating checkpoint reports.
Incorrect
These are the correct activities done during this process:
(a) Accepting the project manager’s work
(b) Creating specialist products
(c) Delivering the specialist products to the project managerThese activities are carried out by the team managers and their teams. Teams regularly report the progress of their work via creating checkpoint reports.
-
Question 5 of 30
5. Question
Which of the following is true about authorizing another delivery stage?
Correct
Authorizing another delivery stage is done by the project board. For this stage, they are responsible for reviewing the next stage plan, updating the business case, and updating the project plan. The project manager will send the end-stage report once all the products are delivered, not before.
Incorrect
Authorizing another delivery stage is done by the project board. For this stage, they are responsible for reviewing the next stage plan, updating the business case, and updating the project plan. The project manager will send the end-stage report once all the products are delivered, not before.
-
Question 6 of 30
6. Question
Which of the following is actions is not done by the project manager in relation for preparing for the end of the project?
Correct
These are done by the project manager at this step:
(a) Ensuring that the ultimate clients accept the project’s products
(b) Creating the end project report and lessons report
(c) Updating the benefits management approach
(d) Archiving the project documentationIncorrect
These are done by the project manager at this step:
(a) Ensuring that the ultimate clients accept the project’s products
(b) Creating the end project report and lessons report
(c) Updating the benefits management approach
(d) Archiving the project documentation -
Question 7 of 30
7. Question
Which of the following is not one of the seven principles of PRINCE2?
Correct
These are the correct seven principles of PRINCE2:
(a) Continued business justification
(b) Learning from experience
(c) Defining roles and responsibilities
(d) Managing by stages
(e) Managing by exception
(f) Focusing on products
(g) Tailoring to suit the project environmentIncorrect
These are the correct seven principles of PRINCE2:
(a) Continued business justification
(b) Learning from experience
(c) Defining roles and responsibilities
(d) Managing by stages
(e) Managing by exception
(f) Focusing on products
(g) Tailoring to suit the project environment -
Question 8 of 30
8. Question
Which of the following activities are done under the starting up a project process?
Correct
These are the correct activities under this process:
(a) Planning the initiation stage
(b) Appointing the executive
(c) Appointing the project manager
(d) Preparing the outline business case
(e) Capturing previous lessons
(f) Design the project management team
(g) Appointing the project management team
(h) Selecting the project approach and the project brief
(i) Planning the initiation stageIncorrect
These are the correct activities under this process:
(a) Planning the initiation stage
(b) Appointing the executive
(c) Appointing the project manager
(d) Preparing the outline business case
(e) Capturing previous lessons
(f) Design the project management team
(g) Appointing the project management team
(h) Selecting the project approach and the project brief
(i) Planning the initiation stage -
Question 9 of 30
9. Question
Which of the following is a part of the project brief?
Correct
Project brief includes creating role descriptions for project manager as well as the executive. Appointing these roles are steps prior to creating the daily log. All of these actions are under the creating the project mandate.
Incorrect
Project brief includes creating role descriptions for project manager as well as the executive. Appointing these roles are steps prior to creating the daily log. All of these actions are under the creating the project mandate.
-
Question 10 of 30
10. Question
Which of the following is true about the daily log?
Correct
A daily log is referred to as the project manager’s diary. It is created by the project manager. It is used to track personal action points and informal issues. These issues are issues that are not tracked by other registers and logs. Daily logs have used a repository until registers are created. Registers are created during the initiating of a project process.
Incorrect
A daily log is referred to as the project manager’s diary. It is created by the project manager. It is used to track personal action points and informal issues. These issues are issues that are not tracked by other registers and logs. Daily logs have used a repository until registers are created. Registers are created during the initiating of a project process.
-
Question 11 of 30
11. Question
Which statement does not describe what the Project Board is?
Correct
The Project Board is responsible for managing the project and ensuring that it delivers the intended business value. The three key participants are the Executive, the Senior Users, and the Senior Suppliers. Quality Assurance and Customer Support are included in this. These two serve as the representative for their respective key function.
Incorrect
The Project Board is responsible for managing the project and ensuring that it delivers the intended business value. The three key participants are the Executive, the Senior Users, and the Senior Suppliers. Quality Assurance and Customer Support are included in this. These two serve as the representative for their respective key function.
-
Question 12 of 30
12. Question
Which of the following correctly describes the Executive?
Correct
The Executive represents the interest of senior management. They also have the responsibility of making the ultimate decisions for the project. Statement 2 refers to Senior Users. Statement 3 and Statement 4 refers to Senior suppliers. Senior suppliers represent either the internal team or the external team.
Incorrect
The Executive represents the interest of senior management. They also have the responsibility of making the ultimate decisions for the project. Statement 2 refers to Senior Users. Statement 3 and Statement 4 refers to Senior suppliers. Senior suppliers represent either the internal team or the external team.
-
Question 13 of 30
13. Question
Which of the following are the correct terms established by the Project Board that a Project Manager must do?
Correct
A Project Manager must do the following:
(a) Allocate work
(b) Provide updates
(c) Manage issues and risks
(d) Monitoring time
(e) Monitoring budget and scope
(f) Monitoring benefit and quality tolerances
(g) Raise exceptionsIncorrect
A Project Manager must do the following:
(a) Allocate work
(b) Provide updates
(c) Manage issues and risks
(d) Monitoring time
(e) Monitoring budget and scope
(f) Monitoring benefit and quality tolerances
(g) Raise exceptions -
Question 14 of 30
14. Question
Which of the following is not included in the objectives of all Agile methods?
Correct
These are the correct objectives of all Agile methods:
(a) Using incremental planning instead of upfront planning
(b) Addressing risks as early in the process as possible
(c) Empowering the staff
(d) Providing continuous business value to the organization
(e) Providing a low-overhead structure to minimize the impact of changing requirements
(f) Relentlessly confirm the solution’s integrity
(g) Encourage ongoing communicationIncorrect
These are the correct objectives of all Agile methods:
(a) Using incremental planning instead of upfront planning
(b) Addressing risks as early in the process as possible
(c) Empowering the staff
(d) Providing continuous business value to the organization
(e) Providing a low-overhead structure to minimize the impact of changing requirements
(f) Relentlessly confirm the solution’s integrity
(g) Encourage ongoing communication -
Question 15 of 30
15. Question
Which of the following is used in communication in relation to the overview of Agile?
Correct
Executive dashboards, Daily Stand-up Meetings, and Iterative Review sessions are used in communication. Communication also includes information Radiators which included work that is completed, work remaining, issues, and risks.
Incorrect
Executive dashboards, Daily Stand-up Meetings, and Iterative Review sessions are used in communication. Communication also includes information Radiators which included work that is completed, work remaining, issues, and risks.
-
Question 16 of 30
16. Question
Which of the following is not under Iterative strategies in relation to Agile methods?
Correct
Iterative strategies are used to manage software development projects. Scrum, Dynamic Systems Development Method, Driven Development, Agile Unified Process, and Rational Unified Process are under this agile method. Scrumban and Kanban are used for managing software development and maintenance and support activities.
Incorrect
Iterative strategies are used to manage software development projects. Scrum, Dynamic Systems Development Method, Driven Development, Agile Unified Process, and Rational Unified Process are under this agile method. Scrumban and Kanban are used for managing software development and maintenance and support activities.
-
Question 17 of 30
17. Question
Which of the following methods is not used to support large enterprise-wide teams and shared corporate objectives?
Correct
These agile methods are used to support large enterprise-wide teams and shared corporate objectives. They have shared corporate objectives. This includes the Scaled Agile Framework, Scrums of Scrums, Nexus, and Large-Scale Scrum Framework. Lean development is used to optimize software development work.
Incorrect
These agile methods are used to support large enterprise-wide teams and shared corporate objectives. They have shared corporate objectives. This includes the Scaled Agile Framework, Scrums of Scrums, Nexus, and Large-Scale Scrum Framework. Lean development is used to optimize software development work.
-
Question 18 of 30
18. Question
Which of the following is used to manage software development?
Correct
Kanban is used to manage software development and maintenance and support activities. Nexus and Scrums of scrums are used to support large enterprise-wide teams. EXtreme Programming is used to optimize software development.
Incorrect
Kanban is used to manage software development and maintenance and support activities. Nexus and Scrums of scrums are used to support large enterprise-wide teams. EXtreme Programming is used to optimize software development.
-
Question 19 of 30
19. Question
Which of the following statements is true about PRINCE2 Agile?
Correct
PRINCE2 Agile is an adaptive governance method for project delivery and it is the first extension module to the PRINCE2 method. It combines PRINCE2 and Agile methods. By doing this is delivers the efficiencies of Agile methods and at the same time maintains PRINCE2’s integrity in terms of its principles, themes, processes, roles, and project artifacts.
Incorrect
PRINCE2 Agile is an adaptive governance method for project delivery and it is the first extension module to the PRINCE2 method. It combines PRINCE2 and Agile methods. By doing this is delivers the efficiencies of Agile methods and at the same time maintains PRINCE2’s integrity in terms of its principles, themes, processes, roles, and project artifacts.
-
Question 20 of 30
20. Question
Which of the following is true about implementing PRINCE2 Agile framework?
Correct
PRINCE2 Agile framework can increase both the rates of on-time and on-budget project delivery. With this, they have project outcomes that continually confirmed to meet the requirements of the business. There is more cohesion between the senior management and project delivery teams. There is transparency for all stakeholders as well as communication. There is the flexibility to adapt to project work to meet changing requirements.
Incorrect
PRINCE2 Agile framework can increase both the rates of on-time and on-budget project delivery. With this, they have project outcomes that continually confirmed to meet the requirements of the business. There is more cohesion between the senior management and project delivery teams. There is transparency for all stakeholders as well as communication. There is the flexibility to adapt to project work to meet changing requirements.
-
Question 21 of 30
21. Question
Which of the following is false about PRINCE2 organizations implementing the PRINCE2 Agile method?
Correct
The Project Board and project manager will continually get information on the project status. They no longer have to wait for highlight reports or checkpoint reports. The project delivery teams are always focused on delivering business-value capabilities at the highest level. This is done all throughout the project. The project delivery teams do work without significant delays and do work without significant reporting overheads.
Incorrect
The Project Board and project manager will continually get information on the project status. They no longer have to wait for highlight reports or checkpoint reports. The project delivery teams are always focused on delivering business-value capabilities at the highest level. This is done all throughout the project. The project delivery teams do work without significant delays and do work without significant reporting overheads.
-
Question 22 of 30
22. Question
What is not a part of the PRINCE2 project governance structure?
Correct
These are a part of the PRINCE2 project governance structure:
(a) Project work driven by the project brief
(b) A structured project delivery approach or the PID
(c) Project oversight
(d) Ongoing management
(e) Ongoing communication of project activitiesIncorrect
These are a part of the PRINCE2 project governance structure:
(a) Project work driven by the project brief
(b) A structured project delivery approach or the PID
(c) Project oversight
(d) Ongoing management
(e) Ongoing communication of project activities -
Question 23 of 30
23. Question
Which of the following is a key touchpoint in the PRINCE2 Agile framework?
Correct
These are the correct key touchpoints in the PRINCE2 Agile framework:
(a) Requirements as outcomes and Acceptance Criteria
(b) Controls and Tolerances
(c) Outputs
(d) Issues and Risks
(e) CommunicationVariables such as Time and cost will be fixed in PRINCE2 Agile. Scope and quality will have expected levels of flexibility while benefits and risks will either be fixed or flexible. This depends on the nature of the project.
Incorrect
These are the correct key touchpoints in the PRINCE2 Agile framework:
(a) Requirements as outcomes and Acceptance Criteria
(b) Controls and Tolerances
(c) Outputs
(d) Issues and Risks
(e) CommunicationVariables such as Time and cost will be fixed in PRINCE2 Agile. Scope and quality will have expected levels of flexibility while benefits and risks will either be fixed or flexible. This depends on the nature of the project.
-
Question 24 of 30
24. Question
Which of the following does not describe the key touchpoint, Control and Tolerances?
Correct
Control and tolerances is used to manage the project variables. There are six project variables which are benefits, scope, time, cost, quality, and risk. These must be managed in accordance with the acceptable levels identified by the Project board. Statement 4 refers to Requirements as outcomes and acceptance criteria.
Incorrect
Control and tolerances is used to manage the project variables. There are six project variables which are benefits, scope, time, cost, quality, and risk. These must be managed in accordance with the acceptable levels identified by the Project board. Statement 4 refers to Requirements as outcomes and acceptance criteria.
-
Question 25 of 30
25. Question
Which of the following does not refer to the key touchpoint, Outputs?
Correct
Outputs are the most important measures of the project process in PRINCE2 Agile. Ongoing business values are potentially releasable capabilities. This is produced by the project delivery team in each management stage. The Project Board determines the ongoing viability of the project and they also approve the subsequent stages.
Incorrect
Outputs are the most important measures of the project process in PRINCE2 Agile. Ongoing business values are potentially releasable capabilities. This is produced by the project delivery team in each management stage. The Project Board determines the ongoing viability of the project and they also approve the subsequent stages.
-
Question 26 of 30
26. Question
Which of the following is true about the key touchpoint, Issues, and Risks?
Correct
The entire delivery team is responsible for identifying issues and risks that can jeopardize the expected outcomes of the projects. It is just not the responsibility of the project manager. High communication is a critical factor in the PRINCE2 Agile project’s success.
Incorrect
The entire delivery team is responsible for identifying issues and risks that can jeopardize the expected outcomes of the projects. It is just not the responsibility of the project manager. High communication is a critical factor in the PRINCE2 Agile project’s success.
-
Question 27 of 30
27. Question
Which of the following is not actions done by the project manager and the team manager?
Correct
The project manager and the team manager sit between Project Governance and Project delivery.
They act as the bridge between the Project Board and the project delivery team. They identify the required work and facilitate good communication between the two. They also escalate issues and ensure compliance with the requirements of the PRINCE2 Agile governance.Incorrect
The project manager and the team manager sit between Project Governance and Project delivery.
They act as the bridge between the Project Board and the project delivery team. They identify the required work and facilitate good communication between the two. They also escalate issues and ensure compliance with the requirements of the PRINCE2 Agile governance. -
Question 28 of 30
28. Question
Which of the following is not a part of the Key Principles of PRINCE2 Agile method?
Correct
These are the correct Key Principles:
(a) Transparency
(b) Collaboration
(c) Communication
(d) Exploration
(e) Self-organization
(f) AccountabilityPRINCE2 Agile fosters and relies upon an environment of the Key Principles said above.
Incorrect
These are the correct Key Principles:
(a) Transparency
(b) Collaboration
(c) Communication
(d) Exploration
(e) Self-organization
(f) AccountabilityPRINCE2 Agile fosters and relies upon an environment of the Key Principles said above.
-
Question 29 of 30
29. Question
Which of the following statements is false about exploration in relation to the Key Principles?
Correct
Exploration empowers the teams to investigate potential solution options but the Project board must understand that not all options that are explored are viable. They must also understand that trialing may require a substantial amount of rework. Some results of this may need the original product requirements to be revisited. Exploration is also used to mitigate risks as early as possible.
Incorrect
Exploration empowers the teams to investigate potential solution options but the Project board must understand that not all options that are explored are viable. They must also understand that trialing may require a substantial amount of rework. Some results of this may need the original product requirements to be revisited. Exploration is also used to mitigate risks as early as possible.
-
Question 30 of 30
30. Question
Which of the following is true about Self-organization in relation to the Key Principles?
Correct
Self-organization empowers the allocation of the project delivery team’s work. They do this to make sure that they utilize the skills and strengths of each member of the team. Statement 2 refers to Collaboration. Statement 3 refers to Communication. Statement 4 refers to Transparency.
Incorrect
Self-organization empowers the allocation of the project delivery team’s work. They do this to make sure that they utilize the skills and strengths of each member of the team. Statement 2 refers to Collaboration. Statement 3 refers to Communication. Statement 4 refers to Transparency.