Quiz-summary
0 of 30 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
Information
Certdemy Premium Access
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 30 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- Answered
- Review
-
Question 1 of 30
1. Question
You work in the financial department in your firm. You have been asked to assist a certain project manager in the cost management for a project. Which among the following is not included in the project cost management process?
Correct
Project Cost Management processes:
1. Plan Cost Management
2. Estimate Costs
3. Determine Budget
4. Control CostsIncorrect
Project Cost Management processes:
1. Plan Cost Management
2. Estimate Costs
3. Determine Budget
4. Control Costs -
Question 2 of 30
2. Question
Which among the following is not true for project cost management process?
Correct
Project Cost Management should consider the stakeholder requirements for managing costs. Different stakeholders will measure project costs in different ways and at different times. Project Cost Management is primarily concerned with the cost of the resources needed to complete project activities. Project Cost Management should also consider the effect of project decisions on the subsequent recurring cost of using, maintaining, and supporting the product, service, or result of the project.
Incorrect
Project Cost Management should consider the stakeholder requirements for managing costs. Different stakeholders will measure project costs in different ways and at different times. Project Cost Management is primarily concerned with the cost of the resources needed to complete project activities. Project Cost Management should also consider the effect of project decisions on the subsequent recurring cost of using, maintaining, and supporting the product, service, or result of the project.
-
Question 3 of 30
3. Question
You work in the financial department in your firm. You have been asked to assist a certain project manager in the cost management for a project. Which among the following defines plan cost management process?
Correct
Plan Cost Management is the process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs. The key benefit of this process is that it provides guidance and direction on how the project costs will be managed throughout the project.
Incorrect
Plan Cost Management is the process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs. The key benefit of this process is that it provides guidance and direction on how the project costs will be managed throughout the project.
-
Question 4 of 30
4. Question
You work in the financial department in your firm. You have been asked to assist a certain project manager in the cost management for a project. Which among the following is not true for plan cost management process?
Correct
Plan Cost Management is the process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs. The key benefit of this process is that it provides guidance and direction on how the project costs will be managed throughout the project. The cost management processes and their associated tools and techniques are documented in the cost management plan. The cost management plan is a component of the project management plan.
Incorrect
Plan Cost Management is the process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs. The key benefit of this process is that it provides guidance and direction on how the project costs will be managed throughout the project. The cost management processes and their associated tools and techniques are documented in the cost management plan. The cost management plan is a component of the project management plan.
-
Question 5 of 30
5. Question
Which among the following is not an input to plan cost management process?
Correct
Plan Cost Management: Inputs
1. Project Management Plan
2. Project Charter
3. Enterprise Environmental Factors
4. Organizational Process AssetsIncorrect
Plan Cost Management: Inputs
1. Project Management Plan
2. Project Charter
3. Enterprise Environmental Factors
4. Organizational Process Assets -
Question 6 of 30
6. Question
You are a project manager in your firm and are currently in the process of planning cost management for your project. Which among the following is not an enterprise environmental factor that affect the plan cost management process?
Correct
The enterprise environmental factors that influence the Plan Cost Management process include:
• Organizational culture and structure
• Market conditions
• Currency exchange rates for project costs sourced from more than one country
• Published commercial information
• Project management information system, which provides alternative possibilities for managing costIncorrect
The enterprise environmental factors that influence the Plan Cost Management process include:
• Organizational culture and structure
• Market conditions
• Currency exchange rates for project costs sourced from more than one country
• Published commercial information
• Project management information system, which provides alternative possibilities for managing cost -
Question 7 of 30
7. Question
You are a project manager in your firm and are currently in the process of planning cost management for your project. Which among the following is not an organizational process assets that affect the plan cost management process?
Correct
The organizational process assets that influence the Plan Cost Management process include:
• Financial controls procedures
• Historical information and lessons learned knowledge bases
• Financial databases
• Existing formal and informal cost estimating and budgeting-related policies, procedures, and guidelinesIncorrect
The organizational process assets that influence the Plan Cost Management process include:
• Financial controls procedures
• Historical information and lessons learned knowledge bases
• Financial databases
• Existing formal and informal cost estimating and budgeting-related policies, procedures, and guidelines -
Question 8 of 30
8. Question
Which of the following is not among the tools and techniques involved in plan cost management process?
Correct
Plan Cost Management: Tools and Techniques
1. Expert Judgment
2. Analytical Techniques
3. MeetingsIncorrect
Plan Cost Management: Tools and Techniques
1. Expert Judgment
2. Analytical Techniques
3. Meetings -
Question 9 of 30
9. Question
You are a business analyst in your firm and have been asked to review the cost management plan for a project. Which among the following defines a cost management plan?
Correct
The cost management plan is a component of the project management plan and describes how the project costs will be planned, structured, and controlled. The cost management processes and their associated tools and techniques are documented in the cost management plan.
Incorrect
The cost management plan is a component of the project management plan and describes how the project costs will be planned, structured, and controlled. The cost management processes and their associated tools and techniques are documented in the cost management plan.
-
Question 10 of 30
10. Question
Which among the following is not established by a cost management plan?
Correct
The cost management plan can establish the following:
• Units of measure
• Level of precision
• Level of accuracy
• Organizational procedures links
• Control thresholds
• Rules of performance measurement
• Reporting formats
• Process descriptionsIncorrect
The cost management plan can establish the following:
• Units of measure
• Level of precision
• Level of accuracy
• Organizational procedures links
• Control thresholds
• Rules of performance measurement
• Reporting formats
• Process descriptions -
Question 11 of 30
11. Question
Which among the following defines the cost estimation process?
Correct
Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of this process is that it determines the amount of cost required to complete project work.
Incorrect
Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of this process is that it determines the amount of cost required to complete project work.
-
Question 12 of 30
12. Question
You work in the financial department in your firm and have been asked to estimate the costs for a certain project. Which among the following is not true for cost estimation project?
Correct
Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of this process is that it determines the amount of cost required to complete project work. Cost estimates are a prediction that is based on the information known at a given point in time. Cost estimates include the identification and consideration of costing alternatives to initiate and complete the project.
Incorrect
Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of this process is that it determines the amount of cost required to complete project work. Cost estimates are a prediction that is based on the information known at a given point in time. Cost estimates include the identification and consideration of costing alternatives to initiate and complete the project.
-
Question 13 of 30
13. Question
Which among the following is not true for cost estimates?
Correct
Cost estimates are a prediction that is based on the information known at a given point in time. Cost estimates include the identification and consideration of costing alternatives to initiate and complete the project. Cost estimates should be reviewed and refined during the course of the project to reflect additional detail as it becomes available and assumptions are tested. The accuracy of a project estimate will increase as the project progresses through the project life cycle. A cost estimate is a quantitative assessment of the likely costs for resources required to complete the activity. Cost estimates may be presented at the activity level or in summary form.
Incorrect
Cost estimates are a prediction that is based on the information known at a given point in time. Cost estimates include the identification and consideration of costing alternatives to initiate and complete the project. Cost estimates should be reviewed and refined during the course of the project to reflect additional detail as it becomes available and assumptions are tested. The accuracy of a project estimate will increase as the project progresses through the project life cycle. A cost estimate is a quantitative assessment of the likely costs for resources required to complete the activity. Cost estimates may be presented at the activity level or in summary form.
-
Question 14 of 30
14. Question
You are a project manager in your firm and are currently in the process of cost estimation for your project. Which among the following is not an input of the estimate cost process?
Correct
Estimate Costs: Inputs
1. Cost Management Plan
2. Human Resource Management Plan
3. Scope Baseline
4. Project Schedule
5. Risk Register
6. Enterprise Environmental Factors
7. Organizational Process AssetsIncorrect
Estimate Costs: Inputs
1. Cost Management Plan
2. Human Resource Management Plan
3. Scope Baseline
4. Project Schedule
5. Risk Register
6. Enterprise Environmental Factors
7. Organizational Process Assets -
Question 15 of 30
15. Question
You are a project manager in your firm and are currently in the process of cost estimation for your project. Which of the following is not among the tools and techniques used in estimate cost process?
Correct
Estimate Costs: Tools and Techniques
1. Expert Judgment
2. Analogous Estimating
3. Parametric Estimating
4. Bottom-Up Estimating
5. Three-Point Estimating
6. Reserve Analysis
7. Cost of QualityIncorrect
Estimate Costs: Tools and Techniques
1. Expert Judgment
2. Analogous Estimating
3. Parametric Estimating
4. Bottom-Up Estimating
5. Three-Point Estimating
6. Reserve Analysis
7. Cost of Quality -
Question 16 of 30
16. Question
You are a project manager and have decided to implement reserve analysis to estimate the cost of your project. Which among the following defines contingency reserves?
Correct
Contingency reserves are the budget within the cost baseline that is allocated for identified risks, which are accepted and for which contingent or mitigating responses are developed. Contingency reserves are often viewed as the part of the budget intended to address the “known-unknowns” that can affect a project.
Incorrect
Contingency reserves are the budget within the cost baseline that is allocated for identified risks, which are accepted and for which contingent or mitigating responses are developed. Contingency reserves are often viewed as the part of the budget intended to address the “known-unknowns” that can affect a project.
-
Question 17 of 30
17. Question
Which among the following is not true for contingency reserves in the estimate cost process?
Correct
Contingency reserves are the budget within the cost baseline that is allocated for identified risks, which are accepted and for which contingent or mitigating responses are developed. Contingency reserves are often viewed as the part of the budget intended to address the “known-unknowns” that can affect a project. Contingency reserves can provide for a specific activity, for the whole project, or both. As more precise information about the project becomes available, the contingency reserve may be used, reduced, or eliminated. Contingency should be clearly identified in cost documentation.
Incorrect
Contingency reserves are the budget within the cost baseline that is allocated for identified risks, which are accepted and for which contingent or mitigating responses are developed. Contingency reserves are often viewed as the part of the budget intended to address the “known-unknowns” that can affect a project. Contingency reserves can provide for a specific activity, for the whole project, or both. As more precise information about the project becomes available, the contingency reserve may be used, reduced, or eliminated. Contingency should be clearly identified in cost documentation.
-
Question 18 of 30
18. Question
You are a project manager and have decided to implement reserve analysis to estimate the cost of your project. Which among the following defines management reserves?
Correct
Management reserves are an amount of the project budget withheld for management control purposes and are reserved for unforeseen work that is within scope of the project. Management reserves are intended to address the “unknown unknowns” that can affect a project.
Incorrect
Management reserves are an amount of the project budget withheld for management control purposes and are reserved for unforeseen work that is within scope of the project. Management reserves are intended to address the “unknown unknowns” that can affect a project.
-
Question 19 of 30
19. Question
Which among the following is not true for contingency reserves in the estimate cost process?
Correct
Management reserves are an amount of the project budget withheld for management control purposes and are reserved for unforeseen work that is within scope of the project. Management reserves are intended to address the “unknown unknowns” that can affect a project. The management reserve is not included in the cost baseline but is part of the overall project budget and funding requirements. When an amount of management reserves is used to fund unforeseen work, the amount of management reserve used is added to the cost baseline, thus requiring an approved change to the cost baseline.
Incorrect
Management reserves are an amount of the project budget withheld for management control purposes and are reserved for unforeseen work that is within scope of the project. Management reserves are intended to address the “unknown unknowns” that can affect a project. The management reserve is not included in the cost baseline but is part of the overall project budget and funding requirements. When an amount of management reserves is used to fund unforeseen work, the amount of management reserve used is added to the cost baseline, thus requiring an approved change to the cost baseline.
-
Question 20 of 30
20. Question
You are a project manager and have decided to implement analogous cost estimating technique to estimate the cost of your project. Which among the following defines analogous cost estimation?
Correct
Analogous cost estimating uses the values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measurement for a current project. When estimating costs, this technique relies on the actual cost of previous, similar projects as the basis for estimating the cost of the current project. It is a gross value estimating approach, sometimes adjusted for known differences in project complexity.
Incorrect
Analogous cost estimating uses the values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measurement for a current project. When estimating costs, this technique relies on the actual cost of previous, similar projects as the basis for estimating the cost of the current project. It is a gross value estimating approach, sometimes adjusted for known differences in project complexity.
-
Question 21 of 30
21. Question
You are a project manager and have decided to implement analogous cost estimating technique to estimate the cost of your project. Which among the following is not true for analogous cost estimation?
Correct
Analogous cost estimating uses the values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measurement for a current project. When estimating costs, this technique relies on the actual cost of previous, similar projects as the basis for estimating the cost of the current project. It is a gross value estimating approach, sometimes adjusted for known differences in project complexity. Analogous cost estimating is frequently used to estimate a value when there is a limited amount of detailed information about the project, for example, in the early phases of a project. Analogous cost estimating uses historical information and expert judgment.
Incorrect
Analogous cost estimating uses the values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measurement for a current project. When estimating costs, this technique relies on the actual cost of previous, similar projects as the basis for estimating the cost of the current project. It is a gross value estimating approach, sometimes adjusted for known differences in project complexity. Analogous cost estimating is frequently used to estimate a value when there is a limited amount of detailed information about the project, for example, in the early phases of a project. Analogous cost estimating uses historical information and expert judgment.
-
Question 22 of 30
22. Question
Which among the following techniques is not included in three-point cost estimation?
Correct
Three-Point Estimating
The accuracy of single-point activity cost estimates may be improved by considering estimation uncertainty and risk and using three estimates to define an approximate range for an activity’s cost:
• Most likely (cM). The cost of the activity, based on realistic effort assessment for the required work and any predicted expenses.
• Optimistic (cO). The activity cost based on analysis of the best-case scenario for the activity.
• Pessimistic (cP). The activity cost based on analysis of the worst-case scenario for the activity.Incorrect
Three-Point Estimating
The accuracy of single-point activity cost estimates may be improved by considering estimation uncertainty and risk and using three estimates to define an approximate range for an activity’s cost:
• Most likely (cM). The cost of the activity, based on realistic effort assessment for the required work and any predicted expenses.
• Optimistic (cO). The activity cost based on analysis of the best-case scenario for the activity.
• Pessimistic (cP). The activity cost based on analysis of the worst-case scenario for the activity. -
Question 23 of 30
23. Question
You are a project manager and have decided to implement three-point estimation to estimate the cost of your project. Which among the following defines most-likely estimate?
Correct
Most likely (cM)
The cost of the activity, based on realistic effort assessment for the required work and any predicted expenses.Incorrect
Most likely (cM)
The cost of the activity, based on realistic effort assessment for the required work and any predicted expenses. -
Question 24 of 30
24. Question
Which among the following defines the pessimistic estimate in three-point cost estimation?
Correct
Pessimistic (cP)
The activity cost based on analysis of the worst-case scenario for the activity.Incorrect
Pessimistic (cP)
The activity cost based on analysis of the worst-case scenario for the activity. -
Question 25 of 30
25. Question
You are a project manager and have decided to implement three-point estimation to estimate the cost of your project. Which among the following defines optimistic estimate?
Correct
Optimistic (cO)
The activity cost based on analysis of the best-case scenario for the activity.Incorrect
Optimistic (cO)
The activity cost based on analysis of the best-case scenario for the activity. -
Question 26 of 30
26. Question
You work in the financial department in an MNC and are well aware of the various inputs and outputs of the cost estimation process for a project. Which among the following is not an output of the cost estimation process?
Correct
Estimate Costs: Outputs
1. Activity Cost Estimates
2. Basis of Estimates
3. Project Documents UpdatesIncorrect
Estimate Costs: Outputs
1. Activity Cost Estimates
2. Basis of Estimates
3. Project Documents Updates -
Question 27 of 30
27. Question
Which among the following defines activity cost estimates?
Correct
Activity cost estimates are quantitative assessments of the probable costs required to complete project work. Cost estimates can be presented in summary form or in detail. Costs are estimated for all resources that are applied to the activity cost estimate.
Incorrect
Activity cost estimates are quantitative assessments of the probable costs required to complete project work. Cost estimates can be presented in summary form or in detail. Costs are estimated for all resources that are applied to the activity cost estimate.
-
Question 28 of 30
28. Question
Which among the following defines the determine budget process?
Correct
Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. The key benefit of this process is that it determines the cost baseline against which project performance can be monitored and controlled.
Incorrect
Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. The key benefit of this process is that it determines the cost baseline against which project performance can be monitored and controlled.
-
Question 29 of 30
29. Question
You work in the human resource department in your firm and have been asked to work with the financial department for determining the budget for a project. Which among the following is not true for determine budget process?
Correct
Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. The key benefit of this process is that it determines the cost baseline against which project performance can be monitored and controlled. A project budget includes all the funds authorized to execute the project. The cost baseline is the approved version of the time-phased project budget, but excludes management reserves.
Incorrect
Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. The key benefit of this process is that it determines the cost baseline against which project performance can be monitored and controlled. A project budget includes all the funds authorized to execute the project. The cost baseline is the approved version of the time-phased project budget, but excludes management reserves.
-
Question 30 of 30
30. Question
Which among the following is not an input to the determine budget process?
Correct
Determine Budget: Inputs
1. Cost Management Plan
2. Scope Baseline
3. Activity Cost Estimates
4. Basis of Estimates
5. Project Schedule
6. Resource Calendars
7. Risk Register
8. Agreements
9. Organizational Process AssetsIncorrect
Determine Budget: Inputs
1. Cost Management Plan
2. Scope Baseline
3. Activity Cost Estimates
4. Basis of Estimates
5. Project Schedule
6. Resource Calendars
7. Risk Register
8. Agreements
9. Organizational Process Assets