Quiz-summary
0 of 30 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
Information
Certdemy Premium Access
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 30 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- Answered
- Review
-
Question 1 of 30
1. Question
Which among the following is not an input to the developing project schedule process?
Correct
Develop Schedule: Inputs
1. Schedule Management Plan
2. Activity List
3. Activity Attributes
4. Project Schedule Network Diagrams
5. Activity Resource Requirements
6. Resource Calendars
7. Activity Duration Estimates
8. Project Scope Statement
9. Risk Register
10. Project Staff Assignments
11. Resource Breakdown Structure
12. Enterprise Environmental Factors
13. Organizational Process AssetsIncorrect
Develop Schedule: Inputs
1. Schedule Management Plan
2. Activity List
3. Activity Attributes
4. Project Schedule Network Diagrams
5. Activity Resource Requirements
6. Resource Calendars
7. Activity Duration Estimates
8. Project Scope Statement
9. Risk Register
10. Project Staff Assignments
11. Resource Breakdown Structure
12. Enterprise Environmental Factors
13. Organizational Process Assets -
Question 2 of 30
2. Question
You are a project manager in your firm and are well aware of the various inputs and outputs of the develop schedule process. Which among the following is not an enterprise environmental factor that may influence the develop schedule process?
Correct
The enterprise environmental factors include:
• Standards,
• Communication channels, and
• Scheduling tool to be used in developing the schedule model.Incorrect
The enterprise environmental factors include:
• Standards,
• Communication channels, and
• Scheduling tool to be used in developing the schedule model. -
Question 3 of 30
3. Question
Which of the following is not among the tools and techniques used in the develop schedule process?
Correct
Develop Schedule: Tools and Techniques
1. Schedule Network Analysis
2. Critical Path Method
3. Critical Chain Method
4. Resource Optimization Techniques
5. Modeling Techniques
6. Leads and Lags
7. Schedule Compression
8. Scheduling ToolIncorrect
Develop Schedule: Tools and Techniques
1. Schedule Network Analysis
2. Critical Path Method
3. Critical Chain Method
4. Resource Optimization Techniques
5. Modeling Techniques
6. Leads and Lags
7. Schedule Compression
8. Scheduling Tool -
Question 4 of 30
4. Question
You work in the human resource department in your firm and are assisting a certain project manager in developing the schedule for the project. Which among the following defines schedule network analysis?
Correct
Schedule network analysis is a technique that generates the project schedule model. It employs various analytical techniques, such as critical path method, critical chain method, what-if analysis, and resource optimization techniques to calculate the early and late start and finish dates for the uncompleted portions of project activities.
Incorrect
Schedule network analysis is a technique that generates the project schedule model. It employs various analytical techniques, such as critical path method, critical chain method, what-if analysis, and resource optimization techniques to calculate the early and late start and finish dates for the uncompleted portions of project activities.
-
Question 5 of 30
5. Question
You work in the human resource department in your firm and are assisting a certain project manager in developing the schedule for the project. Which among the following defines critical path method?
Correct
The critical path method, which is a method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model. This schedule network analysis technique calculates the early start, early finish, late start, and late finish dates for all activities without regard for any resource limitations by performing a forward and backward pass analysis through the schedule network.
Incorrect
The critical path method, which is a method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model. This schedule network analysis technique calculates the early start, early finish, late start, and late finish dates for all activities without regard for any resource limitations by performing a forward and backward pass analysis through the schedule network.
-
Question 6 of 30
6. Question
Which among the following is not true for critical path method?
Correct
The critical path method, which is a method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model. This schedule network analysis technique calculates the early start, early finish, late start, and late finish dates for all activities without regard for any resource limitations by performing a forward and backward pass analysis through the schedule network. A CPM critical path is normally characterized by zero total float on the critical path.
Incorrect
The critical path method, which is a method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model. This schedule network analysis technique calculates the early start, early finish, late start, and late finish dates for all activities without regard for any resource limitations by performing a forward and backward pass analysis through the schedule network. A CPM critical path is normally characterized by zero total float on the critical path.
-
Question 7 of 30
7. Question
You are a project manager in a firm and have decided to use critical chain method for developing the schedule for your project. Which among the following defines critical chain method?
Correct
The critical chain method (CCM) is a schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties. It is developed from the critical path method approach and considers the effects of resource allocation, resource optimization, resource leveling, and activity duration uncertainty on the critical path determined using the critical path method.
Incorrect
The critical chain method (CCM) is a schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties. It is developed from the critical path method approach and considers the effects of resource allocation, resource optimization, resource leveling, and activity duration uncertainty on the critical path determined using the critical path method.
-
Question 8 of 30
8. Question
You work in the human resource department in your firm and are assisting a certain project manager in developing the schedule for the project. Which among the following is not true for critical chain method?
Correct
The critical chain method (CCM) is a schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties. It is developed from the critical path method approach and considers the effects of resource allocation, resource optimization, resource leveling, and activity duration uncertainty on the critical path determined using the critical path method.The critical chain method adds duration buffers that are non-work schedule activities to manage uncertainty. One buffer, placed at the end of the critical chain is known as the project buffer and protects the target finish date from slippage along the critical chain.
Incorrect
The critical chain method (CCM) is a schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties. It is developed from the critical path method approach and considers the effects of resource allocation, resource optimization, resource leveling, and activity duration uncertainty on the critical path determined using the critical path method.The critical chain method adds duration buffers that are non-work schedule activities to manage uncertainty. One buffer, placed at the end of the critical chain is known as the project buffer and protects the target finish date from slippage along the critical chain.
-
Question 9 of 30
9. Question
Which among the following defines feeding buffers used in the critical chain method?
Correct
Feeding buffers are placed at each point where a chain of dependent activities that are not on the critical chain feeds into the critical chain. Feeding buffers thus protect the critical chain from slippage along the feeding chains. The size of each buffer should account for the uncertainty in the duration of the chain of dependent activities leading up to that buffer.
Incorrect
Feeding buffers are placed at each point where a chain of dependent activities that are not on the critical chain feeds into the critical chain. Feeding buffers thus protect the critical chain from slippage along the feeding chains. The size of each buffer should account for the uncertainty in the duration of the chain of dependent activities leading up to that buffer.
-
Question 10 of 30
10. Question
Which among the following is a type of resource optimization technique?
Correct
Examples of resource optimization techniques that can be used to adjust the schedule model due to demand and supply of resources include:
• Resource leveling
• Resource SmoothingIncorrect
Examples of resource optimization techniques that can be used to adjust the schedule model due to demand and supply of resources include:
• Resource leveling
• Resource Smoothing -
Question 11 of 30
11. Question
You are a project manager in your firm and are currently working on resource leveling. Which among the following defines resource leveling?
Correct
Resource leveling.
A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply. Resource leveling can be used when shared or critically required resources are only available at certain times, or in limited quantities, or over-allocated, such as when a resource has been assigned to two or more activities during the same time period or to keep resource usage at a constant level.Incorrect
Resource leveling.
A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply. Resource leveling can be used when shared or critically required resources are only available at certain times, or in limited quantities, or over-allocated, such as when a resource has been assigned to two or more activities during the same time period or to keep resource usage at a constant level. -
Question 12 of 30
12. Question
Which among the following is not true for resource smoothing?
Correct
Resource Smoothing
A technique that adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed certain predefined resource limits. In resource smoothing, as opposed to resource leveling, the project’s critical path is not changed and the completion date may not be delayed. In other words, activities may only be delayed within their free and total float. Thus resource smoothing may not be able to optimize all resources.Incorrect
Resource Smoothing
A technique that adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed certain predefined resource limits. In resource smoothing, as opposed to resource leveling, the project’s critical path is not changed and the completion date may not be delayed. In other words, activities may only be delayed within their free and total float. Thus resource smoothing may not be able to optimize all resources. -
Question 13 of 30
13. Question
You are a project manager in your firm and are currently working on resource smoothing. Which among the following defines resource smoothing?
Correct
Resource Smoothing
A technique that adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed certain predefined resource limits. In resource smoothing, as opposed to resource leveling, the project’s critical path is not changed and the completion date may not be delayed.Incorrect
Resource Smoothing
A technique that adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed certain predefined resource limits. In resource smoothing, as opposed to resource leveling, the project’s critical path is not changed and the completion date may not be delayed. -
Question 14 of 30
14. Question
Which among the following is not true for resource leveling?
Correct
Resource leveling.
A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply. Resource leveling can be used when shared or critically required resources are only available at certain times, or in limited quantities, or over-allocated, such as when a resource has been assigned to two or more activities during the same time period or to keep resource usage at a constant level. Resource leveling can often cause the original critical path to change, usually to increase.Incorrect
Resource leveling.
A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply. Resource leveling can be used when shared or critically required resources are only available at certain times, or in limited quantities, or over-allocated, such as when a resource has been assigned to two or more activities during the same time period or to keep resource usage at a constant level. Resource leveling can often cause the original critical path to change, usually to increase. -
Question 15 of 30
15. Question
While giving the presentation to a client, you had used the term “schedule compression techniques”. The client wants an explanation as he is not clear. Which among the following defines schedule compression techniques?
Correct
Schedule compression techniques are used to shorten the schedule duration without reducing the project scope, in order to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include, but are not limited to:
• Crashing.
• Fast trackingIncorrect
Schedule compression techniques are used to shorten the schedule duration without reducing the project scope, in order to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include, but are not limited to:
• Crashing.
• Fast tracking -
Question 16 of 30
16. Question
Which among the following defines crashing, a schedule compression technique?
Correct
Crashing.
A technique used to shorten the schedule duration for the least incremental cost by adding resources. Examples of crashing include approving overtime, bringing in additional resources, or paying to expedite delivery to activities on the critical path. Crashing works only for activities on the critical path where additional resources will shorten the activity’s duration. Crashing does not always produce a viable alternative and may result in increased risk and/or cost.Incorrect
Crashing.
A technique used to shorten the schedule duration for the least incremental cost by adding resources. Examples of crashing include approving overtime, bringing in additional resources, or paying to expedite delivery to activities on the critical path. Crashing works only for activities on the critical path where additional resources will shorten the activity’s duration. Crashing does not always produce a viable alternative and may result in increased risk and/or cost. -
Question 17 of 30
17. Question
You are a project manager in your firm and are currently working on schedule compression. Which among the following is not true for crashing?
Correct
Crashing.
A technique used to shorten the schedule duration for the least incremental cost by adding resources. Examples of crashing include approving overtime, bringing in additional resources, or paying to expedite delivery to activities on the critical path. Crashing works only for activities on the critical path where additional resources will shorten the activity’s duration. Crashing does not always produce a viable alternative and may result in increased risk and/or cost.Incorrect
Crashing.
A technique used to shorten the schedule duration for the least incremental cost by adding resources. Examples of crashing include approving overtime, bringing in additional resources, or paying to expedite delivery to activities on the critical path. Crashing works only for activities on the critical path where additional resources will shorten the activity’s duration. Crashing does not always produce a viable alternative and may result in increased risk and/or cost. -
Question 18 of 30
18. Question
You are a project manager in your firm and are currently working on schedule compression. Which among the following defines fast tracking?
Correct
Fast tracking.
A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration. An example is constructing the foundation for a building before completing all of the architectural drawings.Incorrect
Fast tracking.
A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration. An example is constructing the foundation for a building before completing all of the architectural drawings. -
Question 19 of 30
19. Question
Which among the following is not true for fast tracking?
Correct
Fast tracking.
A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration. An example is constructing the foundation for a building before completing all of the architectural drawings. Fast tracking may result in rework and increased risk. Fast tracking only works if activities can be overlapped to shorten the project duration.Incorrect
Fast tracking.
A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration. An example is constructing the foundation for a building before completing all of the architectural drawings. Fast tracking may result in rework and increased risk. Fast tracking only works if activities can be overlapped to shorten the project duration. -
Question 20 of 30
20. Question
You are a business analyst in a firm and have been assigned the task of modelling the process of schedule development by using what-if analysis. Which among the following defines what-if scenario analysis?
Correct
What-If Scenario Analysis.
What-if scenario analysis is the process of evaluating scenarios in order to predict their effect, positively or negatively, on project objectives. This is an analysis of the question, “What if the situation represented by scenario ‘X’ happens?”Incorrect
What-If Scenario Analysis.
What-if scenario analysis is the process of evaluating scenarios in order to predict their effect, positively or negatively, on project objectives. This is an analysis of the question, “What if the situation represented by scenario ‘X’ happens?” -
Question 21 of 30
21. Question
Which among the following defines simulation?
Correct
Simulation.
Simulation involves calculating multiple project durations with different sets of activity assumptions, usually using probability distributions constructed from the three-point estimates to account for uncertainty. The most common simulation technique is Monte Carlo analysis in which a distribution of possible activity durations is defined for each activity and used to calculate a distribution of possible outcomes for the total project.Incorrect
Simulation.
Simulation involves calculating multiple project durations with different sets of activity assumptions, usually using probability distributions constructed from the three-point estimates to account for uncertainty. The most common simulation technique is Monte Carlo analysis in which a distribution of possible activity durations is defined for each activity and used to calculate a distribution of possible outcomes for the total project. -
Question 22 of 30
22. Question
You are a project manager in your firm and are well aware of the various inputs and outputs of the estimate activity durations process. Which among the following is not an output of the schedule development process?
Correct
Develop Schedule: Outputs
1. Schedule Baseline
2. Project Schedule
3. Schedule Data
4. Project Calendars
5. Project Management Plan UpdatesIncorrect
Develop Schedule: Outputs
1. Schedule Baseline
2. Project Schedule
3. Schedule Data
4. Project Calendars
5. Project Management Plan Updates -
Question 23 of 30
23. Question
You are a project manager in your firm and are well aware of the various inputs and outputs of the estimate activity durations process. Which among the following defines schedule data?
Correct
The schedule data for the project schedule model is the collection of information for describing and controlling the schedule. The schedule data includes at least the schedule milestones, schedule activities, activity attributes, and documentation of all identified assumptions and constraints.
Incorrect
The schedule data for the project schedule model is the collection of information for describing and controlling the schedule. The schedule data includes at least the schedule milestones, schedule activities, activity attributes, and documentation of all identified assumptions and constraints.
-
Question 24 of 30
24. Question
You are a project manager in your firm and are well aware of the various inputs and outputs of the estimate activity durations process. Which among the following defines a project calendar?
Correct
A project calendar identifies working days and shifts that are available for scheduled activities. It distinguishes time periods in days or parts of days that are available to complete scheduled activities from time periods that are not available. A schedule model may require more than one project calendar to allow for different work periods for some activities to calculate the project schedule.
Incorrect
A project calendar identifies working days and shifts that are available for scheduled activities. It distinguishes time periods in days or parts of days that are available to complete scheduled activities from time periods that are not available. A schedule model may require more than one project calendar to allow for different work periods for some activities to calculate the project schedule.
-
Question 25 of 30
25. Question
Which among the following defines control schedule process?
Correct
Control Schedule is the process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan. The key benefit of this process is that it provides the means to recognize deviation from the plan and take corrective and preventive actions and thus minimize risk.
Incorrect
Control Schedule is the process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan. The key benefit of this process is that it provides the means to recognize deviation from the plan and take corrective and preventive actions and thus minimize risk.
-
Question 26 of 30
26. Question
You are a project manager in your firm and are well aware of the various project management processes. Which among the following is not true for control schedule process?
Correct
Control Schedule is the process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan. The key benefit of this process is that it provides the means to recognize deviation from the plan and take corrective and preventive actions and thus minimize risk. Updating the schedule model requires knowing the actual performance to date. Any change to the schedule baseline can only be approved through the Perform Integrated Change Control process.
Incorrect
Control Schedule is the process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan. The key benefit of this process is that it provides the means to recognize deviation from the plan and take corrective and preventive actions and thus minimize risk. Updating the schedule model requires knowing the actual performance to date. Any change to the schedule baseline can only be approved through the Perform Integrated Change Control process.
-
Question 27 of 30
27. Question
You are a project manager in your firm and are well aware of the various inputs and outputs of control schedule process. Which among the following is not an input to the control schedule process?
Correct
Control Schedule: Inputs
1. Project Management Plan
2. Project Schedule
3. Work Performance Data
4. Project Calendars
5. Schedule Data
6. Organizational Process AssetsIncorrect
Control Schedule: Inputs
1. Project Management Plan
2. Project Schedule
3. Work Performance Data
4. Project Calendars
5. Schedule Data
6. Organizational Process Assets -
Question 28 of 30
28. Question
Which among the following defines trend analysis?
Correct
Trend analysis examines project performance over time to determine whether performance is improving or deteriorating. Graphical analysis techniques are valuable for understanding performance to date and for comparison to future performance goals in the form of completion dates.
Incorrect
Trend analysis examines project performance over time to determine whether performance is improving or deteriorating. Graphical analysis techniques are valuable for understanding performance to date and for comparison to future performance goals in the form of completion dates.
-
Question 29 of 30
29. Question
Which among the following defines schedule forecasts?
Correct
Schedule forecasts are estimates or predictions of conditions and events in the project’s future based on information and knowledge available at the time of the forecast. Forecasts are updated and reissued based on work performance information provided as the project is executed.
Incorrect
Schedule forecasts are estimates or predictions of conditions and events in the project’s future based on information and knowledge available at the time of the forecast. Forecasts are updated and reissued based on work performance information provided as the project is executed.
-
Question 30 of 30
30. Question
You are a project manager in your firm and are well aware of the various inputs and outputs of control schedule process. Which among the following is not an output to the control schedule process?
Correct
Control Schedule: Outputs
1. Work Performance Information
2. Schedule Forecasts
3. Change Requests
4. Project Management Plan Updates
5. Project Documents Updates
6. Organizational Process Assets UpdatesIncorrect
Control Schedule: Outputs
1. Work Performance Information
2. Schedule Forecasts
3. Change Requests
4. Project Management Plan Updates
5. Project Documents Updates
6. Organizational Process Assets Updates