Quiz-summary
0 of 30 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
Information
Certdemy Premium Access
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 30 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- Answered
- Review
-
Question 1 of 30
1. Question
Which among the following is not true for procurement statement of work?
Correct
The procurement SOW describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results. The procurement SOW is written to be clear, complete, and concise. It includes a description of any collateral services required, such as performance reporting or post-project operational support for the procured item. Each individual procurement item requires a SOW; however, multiple products or services can be grouped as one procurement item within a single SOW. The procurement SOW can be revised and refined as required as it moves through the procurement process until incorporated into a signed agreement.
Incorrect
The procurement SOW describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results. The procurement SOW is written to be clear, complete, and concise. It includes a description of any collateral services required, such as performance reporting or post-project operational support for the procured item. Each individual procurement item requires a SOW; however, multiple products or services can be grouped as one procurement item within a single SOW. The procurement SOW can be revised and refined as required as it moves through the procurement process until incorporated into a signed agreement.
-
Question 2 of 30
2. Question
You work in the human resource department in an MNC and are well aware of the various inputs and outputs of planning procurement management. Which among the following defines procurement documents?
Correct
Procurement documents are used to solicit proposals from prospective sellers. The buyer structures procurement documents to facilitate an accurate and complete response from each prospective seller and to facilitate easy evaluation of the responses. These documents include a description of the desired form of the response, the relevant procurement statement of work (SOW) and any required contractual provisions.
Incorrect
Procurement documents are used to solicit proposals from prospective sellers. The buyer structures procurement documents to facilitate an accurate and complete response from each prospective seller and to facilitate easy evaluation of the responses. These documents include a description of the desired form of the response, the relevant procurement statement of work (SOW) and any required contractual provisions.
-
Question 3 of 30
3. Question
You work in the HR department in a firm and have been asked to assist a certain project lead in handling the procurement documents. Which among the following is not true for procurement documents?
Correct
Procurement documents are used to solicit proposals from prospective sellers. The buyer structures procurement documents to facilitate an accurate and complete response from each prospective seller and to facilitate easy evaluation of the responses. These documents include a description of the desired form of the response, the relevant procurement statement of work (SOW) and any required contractual provisions. The complexity and level of detail of the procurement documents should be consistent with the value of, and risks associated with, the planned procurement. Procurement documents are required to be sufficient to ensure consistent, appropriate responses, but flexible enough to allow consideration of any seller suggestions for better ways to satisfy the same requirements.
Incorrect
Procurement documents are used to solicit proposals from prospective sellers. The buyer structures procurement documents to facilitate an accurate and complete response from each prospective seller and to facilitate easy evaluation of the responses. These documents include a description of the desired form of the response, the relevant procurement statement of work (SOW) and any required contractual provisions. The complexity and level of detail of the procurement documents should be consistent with the value of, and risks associated with, the planned procurement. Procurement documents are required to be sufficient to ensure consistent, appropriate responses, but flexible enough to allow consideration of any seller suggestions for better ways to satisfy the same requirements.
-
Question 4 of 30
4. Question
You work in the human resource department in an MNC and are well aware of the various inputs and outputs of planning procurement management. Which among the following defines source selection criteria?
Correct
Source selection criteria are often included as a part of the procurement documents. Such criteria are developed and used to rate or score seller proposals, and can be objective or subjective. Selection criteria may be limited to only the purchase price if the procurement item is readily available from a number of acceptable sellers. Purchase price in this context includes both the cost of the item and all ancillary expenses such as delivery.
Incorrect
Source selection criteria are often included as a part of the procurement documents. Such criteria are developed and used to rate or score seller proposals, and can be objective or subjective. Selection criteria may be limited to only the purchase price if the procurement item is readily available from a number of acceptable sellers. Purchase price in this context includes both the cost of the item and all ancillary expenses such as delivery.
-
Question 5 of 30
5. Question
You work in the project procurement department in a firm and have been asked to assist a certain project manager in conducting procurements. Which among the following defines conduct procurements process?
Correct
Conduct Procurements is the process of obtaining seller responses, selecting a seller, and awarding a contract. The key benefit of this process is that it provides alignment of internal and external stakeholder expectations through established agreements.
Incorrect
Conduct Procurements is the process of obtaining seller responses, selecting a seller, and awarding a contract. The key benefit of this process is that it provides alignment of internal and external stakeholder expectations through established agreements.
-
Question 6 of 30
6. Question
You are a procurement manager in a project and are currently on on the process of controlling procurements. Which among the following is not true for control procurements process?
Correct
Conduct Procurements is the process of obtaining seller responses, selecting a seller, and awarding a contract. The key benefit of this process is that it provides alignment of internal and external stakeholder expectations through established agreements. During the Conduct Procurements process, the team will receive bids or proposals and will apply previously defined selection criteria to select one or more sellers who are qualified to perform the work and acceptable as a seller.
Incorrect
Conduct Procurements is the process of obtaining seller responses, selecting a seller, and awarding a contract. The key benefit of this process is that it provides alignment of internal and external stakeholder expectations through established agreements. During the Conduct Procurements process, the team will receive bids or proposals and will apply previously defined selection criteria to select one or more sellers who are qualified to perform the work and acceptable as a seller.
-
Question 7 of 30
7. Question
You work in the human resource department in an MNC and are well aware of the various inputs and outputs of conducting procurements process. Which among the following is not an input to conduct procurements process?
Correct
Conduct Procurements: Inputs
1. Procurement Management Plan
2. Procurement Documents
3. Source Selection Criteria
4. Seller Proposals
5. Project Documents
6. Make-or-Buy Decisions
7. Procurement Statement of Work
8. Organizational Process AssetsIncorrect
Conduct Procurements: Inputs
1. Procurement Management Plan
2. Procurement Documents
3. Source Selection Criteria
4. Seller Proposals
5. Project Documents
6. Make-or-Buy Decisions
7. Procurement Statement of Work
8. Organizational Process Assets -
Question 8 of 30
8. Question
Which among the following is not a factor that influence make-or-buy decisions?
Correct
Factors that influence make-or-buy decisions may include:
• Core capabilities of the organization,
• Value delivered by vendors meeting the need,
• Risks associated with meeting the need in a cost-effective manner, and
• Capability internally compared with the vendor community.Incorrect
Factors that influence make-or-buy decisions may include:
• Core capabilities of the organization,
• Value delivered by vendors meeting the need,
• Risks associated with meeting the need in a cost-effective manner, and
• Capability internally compared with the vendor community. -
Question 9 of 30
9. Question
You work in the human resource department in an MNC and are well aware of the various tools and techniques used in conducting procurements. Which of the following is not among the tools and techniques used in conduct procurements process?
Correct
Conduct Procurements: Tools and Techniques
1. Bidder Conferences
2. Proposal Evaluation Techniques
3. Independent Estimates
4. Expert Judgment
5. Advertising
6. Analytical Techniques
7. Procurement NegotiationsIncorrect
Conduct Procurements: Tools and Techniques
1. Bidder Conferences
2. Proposal Evaluation Techniques
3. Independent Estimates
4. Expert Judgment
5. Advertising
6. Analytical Techniques
7. Procurement Negotiations -
Question 10 of 30
10. Question
Which among the following defines bidder conference?
Correct
Bidder conferences (sometimes called contractor conferences, vendor conferences, and pre-bid conferences) are meetings between the buyer and all prospective sellers prior to submittal of a bid or proposal. They are used to ensure that all prospective sellers have a clear and common understanding of the procurement requirements), and that no bidders receive preferential treatment.
Incorrect
Bidder conferences (sometimes called contractor conferences, vendor conferences, and pre-bid conferences) are meetings between the buyer and all prospective sellers prior to submittal of a bid or proposal. They are used to ensure that all prospective sellers have a clear and common understanding of the procurement requirements), and that no bidders receive preferential treatment.
-
Question 11 of 30
11. Question
You are a procurement manager for a project in an MNC and have recently decided to conduct bidder conference for some recent procurements. Which among the following is not true for bidder conference?
Correct
Bidder conferences (sometimes called contractor conferences, vendor conferences, and pre-bid conferences) are meetings between the buyer and all prospective sellers prior to submittal of a bid or proposal. They are used to ensure that all prospective sellers have a clear and common understanding of the procurement requirements), and that no bidders receive preferential treatment. To be fair, buyers should take great care to ensure that all prospective sellers hear every question from any individual prospective seller and every answer from the buyer.
Incorrect
Bidder conferences (sometimes called contractor conferences, vendor conferences, and pre-bid conferences) are meetings between the buyer and all prospective sellers prior to submittal of a bid or proposal. They are used to ensure that all prospective sellers have a clear and common understanding of the procurement requirements), and that no bidders receive preferential treatment. To be fair, buyers should take great care to ensure that all prospective sellers hear every question from any individual prospective seller and every answer from the buyer.
-
Question 12 of 30
12. Question
Which among the following defines procurement negotiation?
Correct
Procurement negotiations clarify the structure, requirements, and other terms of the purchases so that mutual agreement can be reached prior to signing the contract. Final contract language reflects all agreements reached. Subjects covered should include responsibilities, authority to make changes, applicable terms and governing law, technical and business management approaches, proprietary rights, contract financing, technical solutions, overall schedule, payments, and price.
Incorrect
Procurement negotiations clarify the structure, requirements, and other terms of the purchases so that mutual agreement can be reached prior to signing the contract. Final contract language reflects all agreements reached. Subjects covered should include responsibilities, authority to make changes, applicable terms and governing law, technical and business management approaches, proprietary rights, contract financing, technical solutions, overall schedule, payments, and price.
-
Question 13 of 30
13. Question
You work in the human resource department in an MNC and are well aware of the various inputs and outputs of conducting procurements. Which among the following is not an output of conduct procurements process?
Correct
Conduct Procurements: Outputs
1. Selected Sellers
2. Agreements
3. Resource Calendars
4. Change Requests
5. Project Management Plan Updates
6. Project Documents UpdatesIncorrect
Conduct Procurements: Outputs
1. Selected Sellers
2. Agreements
3. Resource Calendars
4. Change Requests
5. Project Management Plan Updates
6. Project Documents Updates -
Question 14 of 30
14. Question
Which among the following defines selected sellers?
Correct
The selected sellers are those who have been judged to be in a competitive range based upon the outcome of the proposal or bid evaluation, and who have negotiated a draft contract that will become the actual contract when an award is made. Final approval of all complex, high-value, high-risk procurements will generally require organizational senior management approval prior to award.
Incorrect
The selected sellers are those who have been judged to be in a competitive range based upon the outcome of the proposal or bid evaluation, and who have negotiated a draft contract that will become the actual contract when an award is made. Final approval of all complex, high-value, high-risk procurements will generally require organizational senior management approval prior to award.
-
Question 15 of 30
15. Question
You are a procurement manager for a project in an MNC and are well aware of the various outputs of the conduct procurements process. Which among the following defines a procurement agreement?
Correct
A procurement agreement includes terms and conditions, and may incorporate other items that the buyer specifies regarding what the seller is to perform or provide. It is the project management team’s responsibility to make certain that all agreements meet the specific needs of the project while adhering to organizational procurement policies. Depending upon the application area, an agreement can also be called an understanding, a contract, a subcontract, or a purchase order.
Incorrect
A procurement agreement includes terms and conditions, and may incorporate other items that the buyer specifies regarding what the seller is to perform or provide. It is the project management team’s responsibility to make certain that all agreements meet the specific needs of the project while adhering to organizational procurement policies. Depending upon the application area, an agreement can also be called an understanding, a contract, a subcontract, or a purchase order.
-
Question 16 of 30
16. Question
You are a procurement manager for a project in an MNC and are well aware of the various outputs of the conduct procurements process. Which among the following defines a contract?
Correct
A contract is a mutually binding legal agreement that obligates the seller to provide the specified products, services, or results, and obligates the buyer to compensate the seller. A contract is a legal relationship subject to remedy in the courts.
Incorrect
A contract is a mutually binding legal agreement that obligates the seller to provide the specified products, services, or results, and obligates the buyer to compensate the seller. A contract is a legal relationship subject to remedy in the courts.
-
Question 17 of 30
17. Question
Which among the following is not true for contracts?
Correct
A contract is a mutually binding legal agreement that obligates the seller to provide the specified products, services, or results, and obligates the buyer to compensate the seller. A contract is a legal relationship subject to remedy in the courts.
Incorrect
A contract is a mutually binding legal agreement that obligates the seller to provide the specified products, services, or results, and obligates the buyer to compensate the seller. A contract is a legal relationship subject to remedy in the courts.
-
Question 18 of 30
18. Question
Which among the following is not an element of the project management plan that may be updated as an output of the conduct procurements process?
Correct
Conduct Procurements: Outputs
Elements of the project management plan that may be updated include:
• Cost baseline,
• Scope baseline,
• Schedule baseline,
• Communications management plan, and
• Procurement management plan.Incorrect
Conduct Procurements: Outputs
Elements of the project management plan that may be updated include:
• Cost baseline,
• Scope baseline,
• Schedule baseline,
• Communications management plan, and
• Procurement management plan. -
Question 19 of 30
19. Question
You work in the project procurement department in a firm and have been asked to assist a certain project manager in controlling procurements. Which among the following defines control procurements process?
Correct
Control Procurements is the process of managing procurement relationships, monitoring contract performance, and making changes and corrections to contracts as appropriate. The key benefit of this process is that it ensures that both the seller’s and buyer’s performance meets procurement requirements according to the terms of the legal agreement.
Incorrect
Control Procurements is the process of managing procurement relationships, monitoring contract performance, and making changes and corrections to contracts as appropriate. The key benefit of this process is that it ensures that both the seller’s and buyer’s performance meets procurement requirements according to the terms of the legal agreement.
-
Question 20 of 30
20. Question
You are are project manger and are currently on the process of controlling the procurements for your project. Which among the following is not true for control procurements process?
Correct
Control Procurements is the process of managing procurement relationships, monitoring contract performance, and making changes and corrections to contracts as appropriate. The key benefit of this process is that it ensures that both the seller’s and buyer’s performance meets procurement requirements according to the terms of the legal agreement. Control Procurements also has a financial management component that involves monitoring payments to the seller. The Control Procurements process reviews and documents how well a seller is performing or has performed based on the contract and establishes corrective actions when needed.
Incorrect
Control Procurements is the process of managing procurement relationships, monitoring contract performance, and making changes and corrections to contracts as appropriate. The key benefit of this process is that it ensures that both the seller’s and buyer’s performance meets procurement requirements according to the terms of the legal agreement. Control Procurements also has a financial management component that involves monitoring payments to the seller. The Control Procurements process reviews and documents how well a seller is performing or has performed based on the contract and establishes corrective actions when needed.
-
Question 21 of 30
21. Question
You work in the human resource department in an MNC and are well aware of the various inputs and outputs of controlling procurements process. Which among the following is not an input to control procurements process?
Correct
Control Procurements: Inputs
1. Project Management Plan
2. Procurement Documents
3. Agreements
4. Approved Change Requests
5. Work Performance Reports
6. Work Performance DataIncorrect
Control Procurements: Inputs
1. Project Management Plan
2. Procurement Documents
3. Agreements
4. Approved Change Requests
5. Work Performance Reports
6. Work Performance Data -
Question 22 of 30
22. Question
You work in the human resource department in an MNC and are well aware of the various tools and techniques used in controlling procurements process. Which of the following is not among the tools and techniques used in control procurements process?
Correct
Control Procurements: Tools and Techniques
1. Contract Change Control System
2. Procurement Performance Reviews
3. Inspections and Audits
4. Performance Reporting
5. Payment Systems
6. Claims Administration
7. Records Management SystemIncorrect
Control Procurements: Tools and Techniques
1. Contract Change Control System
2. Procurement Performance Reviews
3. Inspections and Audits
4. Performance Reporting
5. Payment Systems
6. Claims Administration
7. Records Management System -
Question 23 of 30
23. Question
Which among the following defines a contract change control system?
Correct
A contract change control system defines the process by which the procurement can be modified. It includes the paperwork, tracking systems, dispute resolution procedures, and approval levels necessary for authorizing changes. The contract change control system is integrated with the integrated change control system.
Incorrect
A contract change control system defines the process by which the procurement can be modified. It includes the paperwork, tracking systems, dispute resolution procedures, and approval levels necessary for authorizing changes. The contract change control system is integrated with the integrated change control system.
-
Question 24 of 30
24. Question
While in a client meeting, you have used the term “procurement performance review”. The client wants an explanation as he is not aware of the process. Which among the following defines a procurement performance review?
Correct
A procurement performance review is a structured review of the seller’s progress to deliver project scope and quality, within cost and on schedule, as compared to the contract. It can include a review of seller-prepared documentation and buyer inspections, as well as quality audits conducted during seller’s execution of the work.
Incorrect
A procurement performance review is a structured review of the seller’s progress to deliver project scope and quality, within cost and on schedule, as compared to the contract. It can include a review of seller-prepared documentation and buyer inspections, as well as quality audits conducted during seller’s execution of the work.
-
Question 25 of 30
25. Question
You work in the human resource department in an MNC and are well aware of the various inputs and outputs of controlling procurements process. Which among the following is not an output of control procurements process?
Correct
Control Procurements: Outputs
1. Work Performance Information
2. Change Requests
3. Project Management Plan Updates
4. Project Documents Updates
5. Organizational Process Assets UpdatesIncorrect
Control Procurements: Outputs
1. Work Performance Information
2. Change Requests
3. Project Management Plan Updates
4. Project Documents Updates
5. Organizational Process Assets Updates -
Question 26 of 30
26. Question
Which among the following defines close procurements process?
Correct
Close Procurements is the process of completing each procurement. The key benefit of this process is that it documents agreements and related documentation for future reference. The Close Procurements process also involves administrative activities such as finalizing open claims, updating records to reflect final results, and archiving such information for future use.
Incorrect
Close Procurements is the process of completing each procurement. The key benefit of this process is that it documents agreements and related documentation for future reference. The Close Procurements process also involves administrative activities such as finalizing open claims, updating records to reflect final results, and archiving such information for future use.
-
Question 27 of 30
27. Question
You work in the human resource department in a firm and have been asked to assist a certain project manager in closing procurements of a project. Which among the following is not true for close procurements process?
Correct
Close Procurements is the process of completing each procurement. The key benefit of this process is that it documents agreements and related documentation for future reference. The Close Procurements process also involves administrative activities such as finalizing open claims, updating records to reflect final results, and archiving such information for future use. Close Procurements addresses each contract applicable to the project or a project phase. In multiphase projects, the term of a contract may only be applicable to a given phase of the project. In these cases, the Close Procurements process closes the procurement(s) applicable to that phase of the project. Unresolved claims may be subject to litigation after closure.
Incorrect
Close Procurements is the process of completing each procurement. The key benefit of this process is that it documents agreements and related documentation for future reference. The Close Procurements process also involves administrative activities such as finalizing open claims, updating records to reflect final results, and archiving such information for future use. Close Procurements addresses each contract applicable to the project or a project phase. In multiphase projects, the term of a contract may only be applicable to a given phase of the project. In these cases, the Close Procurements process closes the procurement(s) applicable to that phase of the project. Unresolved claims may be subject to litigation after closure.
-
Question 28 of 30
28. Question
You work in the human resource department in an MNC and are well aware of the various tools and techniques used in closing procurements process. Which of the following is not among the tools and techniques used in close procurements process?
Correct
Close Procurements: Tools and Techniques
1. Procurement Audits
2. Procurement Negotiations
3. Records Management SystemIncorrect
Close Procurements: Tools and Techniques
1. Procurement Audits
2. Procurement Negotiations
3. Records Management System -
Question 29 of 30
29. Question
Which among the following defines a procurement audit?
Correct
A procurement audit is a structured review of the procurement process originating from the Plan Procurement Management process through Control Procurements. The objective of a procurement audit is to identify successes and failures that warrant recognition in the preparation or administration of other procurement contracts on the project, or on other projects within the performing organization.
Incorrect
A procurement audit is a structured review of the procurement process originating from the Plan Procurement Management process through Control Procurements. The objective of a procurement audit is to identify successes and failures that warrant recognition in the preparation or administration of other procurement contracts on the project, or on other projects within the performing organization.
-
Question 30 of 30
30. Question
You are a project manager and have decided to use records management system for closing procurements of your project. Which among the following defines a record management system?
Correct
A records management system is used by the project manager to manage contract and procurement documentation and records. Contract documents and correspondence are archived through the records management system as part of the Close Procurements process.
Incorrect
A records management system is used by the project manager to manage contract and procurement documentation and records. Contract documents and correspondence are archived through the records management system as part of the Close Procurements process.