Quiz-summary
0 of 30 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
Information
Certdemy Premium Access
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 30 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- Answered
- Review
-
Question 1 of 30
1. Question
Richard, from another department, is deputising while the assigned project manager is on long leave. While collecting project status, Richard finds discrepancy in status from past few weeks. The project is overspent, behind schedule. and actually in RED but shown Green on reports. What should Richard do?
Correct
Richard being honest with his work place should Update actual status to dashboard report and inform the management
Incorrect
Richard being honest with his work place should Update actual status to dashboard report and inform the management
-
Question 2 of 30
2. Question
Which of the following is one of the requirements for successful implementation of strategies through projects?
Correct
For successful implementation of strategies the project team must involve allocation of resources , prioritization of projects and motivation of major contributors by adequately planning
Incorrect
For successful implementation of strategies the project team must involve allocation of resources , prioritization of projects and motivation of major contributors by adequately planning
-
Question 3 of 30
3. Question
Which of these is not part of the “technical dimension” of project management?
Correct
In agile methodologies the problem solving is not the part of technical dimension of project management
Incorrect
In agile methodologies the problem solving is not the part of technical dimension of project management
-
Question 4 of 30
4. Question
Which of the following project one must pursue?
Project A having NPV: $3500,
Project B has NPV: $150,
Project C has NPV: $40000,
Project D has NPV: $3000Correct
Choose the Project B with the highest NPV.
Incorrect
Choose the Project B with the highest NPV.
-
Question 5 of 30
5. Question
What is the main way that a Scrum Master contributes to maximising the productivity in the development team?
Correct
A Scrum Master contributes to maximising the productivity in the development team by facilitating Development Team decisions and removing impediments
Incorrect
A Scrum Master contributes to maximising the productivity in the development team by facilitating Development Team decisions and removing impediments
-
Question 6 of 30
6. Question
In order to encourage innovation and creativity establishment of agile emphasises on developing what kind of environment?
Correct
An important reason for creating empowered teams is that it is essential for projects that require creativity and innovation
Incorrect
An important reason for creating empowered teams is that it is essential for projects that require creativity and innovation
-
Question 7 of 30
7. Question
Such managers who underestimate the importance of their project towards the plan of action of their organization makes the following mistake except
Correct
Main roles of manager includes managing the staff and also planning their activities and evaluating their work and efficacy and also to fulfill the provided tasks within the given time span
Incorrect
Main roles of manager includes managing the staff and also planning their activities and evaluating their work and efficacy and also to fulfill the provided tasks within the given time span
-
Question 8 of 30
8. Question
The Development Team is expected to have all the skills needed for which of the following purpose?
Correct
The main reason for which a development team needed to have all the skills in order to turn the Product Backlog items into potentially shippable product increments
Incorrect
The main reason for which a development team needed to have all the skills in order to turn the Product Backlog items into potentially shippable product increments
-
Question 9 of 30
9. Question
Richard is conducting a retrospective meeting. As recommended by the Agile coach, Richard is planning on using the following agenda in the meeting
Correct
Set the stage, gather data, generate insight, decide what to do, close the retrospective is the actual agenda which can be used by Richard in his retrospective meeting
Incorrect
Set the stage, gather data, generate insight, decide what to do, close the retrospective is the actual agenda which can be used by Richard in his retrospective meeting
-
Question 10 of 30
10. Question
A process that involves continuously improving and detailing a plan as more detail become available is termed as
Correct
Progressive elaboration involves continuously improving and detailing a plan as more detailed and specific information and more accurate estimates become available
Incorrect
Progressive elaboration involves continuously improving and detailing a plan as more detailed and specific information and more accurate estimates become available
-
Question 11 of 30
11. Question
The easiest and most commonly used technique for analyzing risks is can be termed as the following :
Correct
Scenario analysis is a process of analyzing future events by considering alternative possible outcomes
Incorrect
Scenario analysis is a process of analyzing future events by considering alternative possible outcomes
-
Question 12 of 30
12. Question
A risk profile is a list of questions that address traditional areas of uncertainty on a project that answers developed from:
Correct
A risk profile is an evaluation of an individual’s willingness and ability to take risks
Incorrect
A risk profile is an evaluation of an individual’s willingness and ability to take risks
-
Question 13 of 30
13. Question
The risk assessment form contains all of the following except :
Correct
The risk assessment form comprises of identification of problem , decision of harmfulness , evaluation of control measures , recording the findings ans then review
Incorrect
The risk assessment form comprises of identification of problem , decision of harmfulness , evaluation of control measures , recording the findings ans then review
-
Question 14 of 30
14. Question
Which of the following is not one of the probability analysis tool?
Correct
The Probability Analysis interface enables you to assess a trade’s potential for movement and manage the potential risk involved
Incorrect
The Probability Analysis interface enables you to assess a trade’s potential for movement and manage the potential risk involved
-
Question 15 of 30
15. Question
The demolition of the Seattle King dome is an example of which of the following?
Correct
The demolition of the Seattle King dome is an example of Mitigating
Incorrect
The demolition of the Seattle King dome is an example of Mitigating
-
Question 16 of 30
16. Question
Technical risks can stop all the ongoing activities.Which of the following depicts the technical risks?
Correct
Technical risk is the possible impact changes could have on a project, system, or entire infrastructure when an implementation does not work as anticipated
Incorrect
Technical risk is the possible impact changes could have on a project, system, or entire infrastructure when an implementation does not work as anticipated
-
Question 17 of 30
17. Question
Among st the following which are the important features of agile project management?
Correct
In Agile, customer engagement is at the very top. The customer is regarded highly in its frameworks as after every iteration, feedback is generated and acted upon.Each team is managed by itself without external guidance
Incorrect
In Agile, customer engagement is at the very top. The customer is regarded highly in its frameworks as after every iteration, feedback is generated and acted upon.Each team is managed by itself without external guidance
-
Question 18 of 30
18. Question
Which of the following changes are observed when a team adopts the shift-left testing approach?
Correct
Focus changes from detecting to preventing defects ,Break the silos between the development and testing teams , Development and testing activities progress in parallel are observed when a team adopts the shift-left testing approach
Incorrect
Focus changes from detecting to preventing defects ,Break the silos between the development and testing teams , Development and testing activities progress in parallel are observed when a team adopts the shift-left testing approach
-
Question 19 of 30
19. Question
Agile development encourages establishment of creating an environment which :
Correct
An important reason for creating empowered teams is that it is essential for projects that require creativity and innovation
Incorrect
An important reason for creating empowered teams is that it is essential for projects that require creativity and innovation
-
Question 20 of 30
20. Question
An important application with the Agile values is that they are predetermined to be
Correct
A very important characteristic of all Agile Manifesto values is that they are intended to be relative statements and not absolutes and they have to be interpreted in the context of the situation
Incorrect
A very important characteristic of all Agile Manifesto values is that they are intended to be relative statements and not absolutes and they have to be interpreted in the context of the situation
-
Question 21 of 30
21. Question
Which Agile Manifesto Value would be most relevant to this situation:
A customer realized in the middle of a project that what was being built will not really meet his needs and a very different solution is more appropriate; however, the new approach will significantly increase the cost and schedule for completing the effortCorrect
The fourth answer is most relevant to this situation In this situation, an appropriate response might be to make the customer and business sponsor aware of the impact of the change and if the customer and business sponsor agrees that it is the right thing to do, go ahead and implement the change
Incorrect
The fourth answer is most relevant to this situation In this situation, an appropriate response might be to make the customer and business sponsor aware of the impact of the change and if the customer and business sponsor agrees that it is the right thing to do, go ahead and implement the change
-
Question 22 of 30
22. Question
“The team, not the leader, gets the real work done.” belongs to:
Correct
Team work is greatly influenced by the management
Incorrect
Team work is greatly influenced by the management
-
Question 23 of 30
23. Question
The N2 Effect can be easily defined as :
Correct
the N2 component has been described in tasks that reflect stimulus identification, attention shifts, inhibition of motor responses, overcoming stereotypical responses or conflict monitoring, maintenance of context information, response selection timing, and detection of novelty or mismatch
Incorrect
the N2 component has been described in tasks that reflect stimulus identification, attention shifts, inhibition of motor responses, overcoming stereotypical responses or conflict monitoring, maintenance of context information, response selection timing, and detection of novelty or mismatch
-
Question 24 of 30
24. Question
Among st the following which is multi criteria selection model?
Correct
In this model ,the parameters of the alternatives are determined by the grey relational grade and expressed in terms of intervals
Incorrect
In this model ,the parameters of the alternatives are determined by the grey relational grade and expressed in terms of intervals
-
Question 25 of 30
25. Question
The cost impact of a risk event occurring as a project proceeds through its life cycle tends to :
Correct
Higher levels of risk tolerance will increase the price of such assets, low levels will reduce those prices
Incorrect
Higher levels of risk tolerance will increase the price of such assets, low levels will reduce those prices
-
Question 26 of 30
26. Question
One common mistake made early in the risk identification process is :
Correct
Risk identification is the process of determining risks that could potentially prevent the program, enterprise, or investment from achieving its objectives
Incorrect
Risk identification is the process of determining risks that could potentially prevent the program, enterprise, or investment from achieving its objectives
-
Question 27 of 30
27. Question
Bill has worked hard over the last few days and finds that the build is broken because Richard has checked in code without properly unit testing it. It will mean that Bill will have to wait until Richard comes back and fixes the issue. Bill is furious at Richard and he makes statements like, “I know Richard. He is always careless and doesn’t bother how others get affected by his actions.”
Which stage of conflict do you think is reflected in Bill’s language?Correct
There are five stages in a conflict. These are latent conflict, perceived conflict, felt conflict, manifest conflict, and conflict aftermath
Incorrect
There are five stages in a conflict. These are latent conflict, perceived conflict, felt conflict, manifest conflict, and conflict aftermath
-
Question 28 of 30
28. Question
All of the following are included in the risk identification process except
Correct
A competitor is the one who is always engaged in commercial and economic competition with other company or organizations
Incorrect
A competitor is the one who is always engaged in commercial and economic competition with other company or organizations
-
Question 29 of 30
29. Question
Retrospective is best described as?
Correct
Retrospective study can be defined as Review how the team worked and not on what was delivered. Take the learning on what could be improved and feed that as input to next iteration
Incorrect
Retrospective study can be defined as Review how the team worked and not on what was delivered. Take the learning on what could be improved and feed that as input to next iteration
-
Question 30 of 30
30. Question
Change management systems are designed to accomplish all of the following except:
Correct
Change management systems are used improve the quality of changes by ensuring that a standard methodology is used to handle all changes and control the impact upon the day-to-day operations of the organization
Incorrect
Change management systems are used improve the quality of changes by ensuring that a standard methodology is used to handle all changes and control the impact upon the day-to-day operations of the organization