Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
Certdemy Premium Access
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 10 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
What does the privilege of granting the organization and project team the flexibility to roles, processes, artifacts needed especially for the project make PRINCE2 Agile?
Correct
PRINCE2 Agile is Agile agnostic because it provides the organization and the project team the flexibility to determine what roles, processes, and artifacts specifically needed for the project.
Incorrect
PRINCE2 Agile is Agile agnostic because it provides the organization and the project team the flexibility to determine what roles, processes, and artifacts specifically needed for the project.
-
Question 2 of 10
2. Question
The PRINCE2 governance structure includes the following except
Correct
The PRINCE2 governance has a well-organized structure that gives room for delivering the required business value
Incorrect
The PRINCE2 governance has a well-organized structure that gives room for delivering the required business value
-
Question 3 of 10
3. Question
The key touchpoints that allow PRINCE2 and Agile to work cohesively in PRINCE2 Agile framework include the following except
Correct
These key touchpoints are enabling drivers that allow the PRINCE2 and Agile to work together in a PRINCE2 Agile framework to achieve the desired results.
Incorrect
These key touchpoints are enabling drivers that allow the PRINCE2 and Agile to work together in a PRINCE2 Agile framework to achieve the desired results.
-
Question 4 of 10
4. Question
What are the most important measures of project progress and ongoing business value in PRINCE2 Agile?
Correct
Outputs are the most important measures of project progress and ongoing business value in PRINCE2 Agile.
Incorrect
Outputs are the most important measures of project progress and ongoing business value in PRINCE2 Agile.
-
Question 5 of 10
5. Question
There are values in PRINCE2 Agile that makes the method work efficiently. Which of these values are expected to be flexible and fixed respectively in the project?
Correct
PRINCE2 Agile lives with the expectation that some variables are to be fixed (time & cost), while some will be flexible (scope and quality) and some will depend on the nature of the project (benefit and risk).
Incorrect
PRINCE2 Agile lives with the expectation that some variables are to be fixed (time & cost), while some will be flexible (scope and quality) and some will depend on the nature of the project (benefit and risk).
-
Question 6 of 10
6. Question
Whose responsibility is it to discover risk and issues in the PRINCE2 Agile framework?
Correct
It is the responsibility of the entire project delivery team to discover and resolve issues and risks.
Incorrect
It is the responsibility of the entire project delivery team to discover and resolve issues and risks.
-
Question 7 of 10
7. Question
In PRINCE2 Agile project, one of these variables is not to be managed in the progress of the project in accordance with the acceptable levels as identified by the project board
Correct
In PRINCE2 Agile, controls and tolerance play a vital role as it helps determine and manage variables as project progresses
Incorrect
In PRINCE2 Agile, controls and tolerance play a vital role as it helps determine and manage variables as project progresses
-
Question 8 of 10
8. Question
What do requirements as outcomes and acceptance criteria mean as a key touchpoint in PRINCE2 Agile?
Correct
Requirements as outcomes and acceptance criteria is one of the key touchpoints that allow PRINCE2 and Agile methods to work cohesively in a PRINCE2 Agile framework.
Incorrect
Requirements as outcomes and acceptance criteria is one of the key touchpoints that allow PRINCE2 and Agile methods to work cohesively in a PRINCE2 Agile framework.
-
Question 9 of 10
9. Question
What is one of the significant measures to be determined by the project board in the course of the project to ascertain the ongoing viability of the project and approve subsequent stages?
Correct
Business value is a significant measure the project board must determine in other to be sure of the viability of the project and approve subsequent stages.
Incorrect
Business value is a significant measure the project board must determine in other to be sure of the viability of the project and approve subsequent stages.
-
Question 10 of 10
10. Question
There are various factors that facilitate the success of PRINCE2 Agile projects. What is the critical factor amongst others to the success of PRINCE2 Agile projects?
Correct
Communication is a critical factor in the success of the PRINCE2 Agile projects because it is an overarching, continuous, bidirectional connection between the Project Board and the project delivery team
Incorrect
Communication is a critical factor in the success of the PRINCE2 Agile projects because it is an overarching, continuous, bidirectional connection between the Project Board and the project delivery team