Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
Practice questions
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 10 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
The inspector will expect to record an ohmic value when measuring the Zs at the new installation’s DB:
Correct
Initially, the inspector may assess the predicted calculated value of the impedance of the earth’s fault loop (Zs) with a simple calculation.
Incorrect
Initially, the inspector may assess the predicted calculated value of the impedance of the earth’s fault loop (Zs) with a simple calculation.
-
Question 2 of 10
2. Question
What reference method should be reported by the inspector on the test schedule the results for the delivery cable between the installation’s origin and the new DB?
Correct
Five core thermoplastic 70 ° C armored steel wire (swa) 10 mm 2 Cables have been mounted between the two in a 50-meter concrete service duct. Buildings; therefore, reference should be made to Appendix 4 of BS 7671.
Incorrect
Five core thermoplastic 70 ° C armored steel wire (swa) 10 mm 2 Cables have been mounted between the two in a 50-meter concrete service duct. Buildings; therefore, reference should be made to Appendix 4 of BS 7671.
-
Question 3 of 10
3. Question
In the new building, the metal water pipe is connected to the earthing terminal within the new building; the inspector is to carry out a continuity examination on the protective conductor, which is 30 meters long with a circumference of 6 mm2. Provide the type of instrument to be used for the test, the steps to be taken to ensure that the test result is correct, and the procedure to be used for the test.
Correct
To guarantee the reliability of the continuity reading, the instrument’s calibration shall be in date, the resistance of the leads of the instrument shall be nullified or, instead, their ohmic value shall be subtracted from the final test result and Test Method 2 (walking or long lead) shall be used, with one end of the bonding conductor removed from the metal pipe.
Incorrect
To guarantee the reliability of the continuity reading, the instrument’s calibration shall be in date, the resistance of the leads of the instrument shall be nullified or, instead, their ohmic value shall be subtracted from the final test result and Test Method 2 (walking or long lead) shall be used, with one end of the bonding conductor removed from the metal pipe.
-
Question 4 of 10
4. Question
Determine the 30 meters, 6 mm2 single-core cable ohmic value.
Correct
Length 30 meter
3.08 m/m cable resistance @ 20° Cable resistance
C
30 for 3.08/1000 = 0.0924 for
Answer: 0.09 (to two decimal places).Incorrect
Length 30 meter
3.08 m/m cable resistance @ 20° Cable resistance
C
30 for 3.08/1000 = 0.0924 for
Answer: 0.09 (to two decimal places). -
Question 5 of 10
5. Question
The latest installation’s metal trunking is to be inspected. What’s going to be the confirming the inspector?
Correct
The inspector must initially check that the trunking has been securely erected for apparent reasons. To provide fault protection, the trunking must be earthed; thus, all joints must be mechanically sound, and this will be confirmed by a continuity test.
Incorrect
The inspector must initially check that the trunking has been securely erected for apparent reasons. To provide fault protection, the trunking must be earthed; thus, all joints must be mechanically sound, and this will be confirmed by a continuity test.
-
Question 6 of 10
6. Question
What data does the inspector report on the electrical installation certificate with respect to conductors of bonding?
Correct
The following bonding conductor characteristics will be registered by the inspector:
I Material (usually copper)
(ii) Cross-sectional area in millimetres (CSA) (mm2)
(iii) Checked connection/continuity (in the associated box, with a tick.Incorrect
The following bonding conductor characteristics will be registered by the inspector:
I Material (usually copper)
(ii) Cross-sectional area in millimetres (CSA) (mm2)
(iii) Checked connection/continuity (in the associated box, with a tick. -
Question 7 of 10
7. Question
The inspector must conduct a prospective fault current test on the inspector on the to mount. What is this test’s purpose?
Correct
The aim of the prospective current fault test is to ensure that the current fault test is the maximum fault current must not surpass the protective device’s Icn rating; this value is typically provided in a rectangular box on a circuit breaker, ensuring the maximum fault current can be safely disrupted by the circuit breaker.
Incorrect
The aim of the prospective current fault test is to ensure that the current fault test is the maximum fault current must not surpass the protective device’s Icn rating; this value is typically provided in a rectangular box on a circuit breaker, ensuring the maximum fault current can be safely disrupted by the circuit breaker.
-
Question 8 of 10
8. Question
The inspector is required to decide the prospective current of fault at each Specific installation point; with the initial reading taken at the origin of the installation; What would the inspector observe when readings are taken at any appropriate point in the facility?
Correct
The resistance of the installation will increase at each appropriate point the root is downstream. The primary explanation for this rise is the length(s) of the built distribution cable(s) and their CSA.
Incorrect
The resistance of the installation will increase at each appropriate point the root is downstream. The primary explanation for this rise is the length(s) of the built distribution cable(s) and their CSA.
-
Question 9 of 10
9. Question
The inspector at the mounted distribution board can use a phase revolving disc instrument. What is the key reason why this examination is conducted by the inspector and where will the outcome be recorded?
Correct
In the case of polyphase circuits, the phase sequence must be verified; in other words, all three-phase circuits must be checked to ensure that the polarity is right and this is done by means of a phase rotating instrument.
Incorrect
In the case of polyphase circuits, the phase sequence must be verified; in other words, all three-phase circuits must be checked to ensure that the polarity is right and this is done by means of a phase rotating instrument.
-
Question 10 of 10
10. Question
State the aim of the periodic inspection and test.
Correct
The object of the issue needs periodic inspection and testing. The inspector must also ensure that the construction is in satisfactory condition.it can also continue to be safely used
Incorrect
The object of the issue needs periodic inspection and testing. The inspector must also ensure that the construction is in satisfactory condition.it can also continue to be safely used